WF quick win detailed plan

Detailed Plan Distribution
Phase/Milestone
Task
Status
Start
End
Notes
Assigned to
[Milestone] Distribute Yearly Budget
Jul 11
Nov 4
Define position creation behavior
Jul 11
Jul 31
PO | SA
Write user stories and acceptance criteria
Aug 10
Aug 18
PO
Design budget tracker solution
Aug 1
Aug 5
PO | SA
Maintain the solution integrity and behavior
Aug 22
Nov 4
PO | SA
[Phase] Develop the ERP budget tracker
Aug 8
Sep 30
Build distributed budget setup
Aug 8
Aug 12
ERP
Store distributed budget of each hiring type per sector
Aug 15
Aug 19
ERP
Submit distributed budget to ERP Budget setup
Aug 15
Aug 26
ESB | BE | FE
Build an APIs to retrieve planning lookups
Aug 22
Sep 2
ERP
Retrieve planning list of values
Sep 5
Sep 9
ESB | BE | FE
Build an API to calculate need cost per hiring type
Sep 5
Sep 9
ERP
Calculate the requested need cost
Sep 12
Sep 16
ESB | BE | FE
Develop alghoritm (BR) to validate the submitted plan
Sep 5
Sep 9
ERP
Build organization pockets structure “budget tracker”
Sep 12
Sep 30
ERP
Validate the saved draft/submitted plan
Sep 12
Sep 23
ESB | BE | FE
Show retrieved validation error message and enable edit actions
Sep 26
Oct 14
ESB | BE | FE
Refactor planning components, improve usability and performance
Aug 15
Sep 23
FE
Prepare test data for test cycles
Sep 12
Sep 23
QA | ERP
Execute system testing on budget distribution/planning
Sep 26
Oct 21
QA
Fix issues and data preparation
Sep 26
Oct 21
ERP | ESB | BE | FE
Specify test plan and test cases
Aug 22
Sep 30
QA
[Phase] Develop position auto creation services
Oct 3
Oct 21
Store planned vacant positions
Oct 3
Oct 14
ERP
Integrate with ERP to build new vacant positions/budget
Oct 17
Oct 21
ESB | BE | FE
Test the auto creation of budget/position
Oct 24
Nov 4
QA
Fix issues and data preparation
Oct 24
Nov 4
ERP | ESB | BE | FE
[Milestone]Conduct BAT on Distribution with budget
Nov 4
Nov 4
Dry run with real business data prior go to production
Nov 7
Nov 18
Prepare production deployment
Nov 21
Nov 25
There are no rows in this table

___ ___ ___

Detailed Plan Maintenance
Phase/Milestone
Task
Status
Start
End
Notes
[Milestone] Maintain Vacant Positions
Aug 8
Nov 18
[Phase] Analysis & Design
Aug 8
Aug 26
Define business flow, requirements, screen
Aug 8
Aug 19
Obtain business approval on service behavior
Aug 22
Aug 26
Design position maintenance service
Aug 22
Aug 26
[Phase] Develop ERP Components
Oct 17
Oct 28
Develop API to get organization pockets
Oct 17
Oct 21
Develop API to get planned vacant positions
Oct 17
Oct 21
Develop API to get position details
Oct 17
Oct 21
Provide an APIs to retrieve maintenance lookups
Oct 17
Oct 21
Develop API to calculate available budget
Oct 17
Oct 21
Develop API to update vacant position attributes
Oct 24
Oct 28
Develop API to modify position status
Oct 24
Oct 28
[Phase] Develop maintenance service
Aug 29
Nov 18
Develop maintenance service workflow
Aug 29
Oct 7
Develop maintenance service interface UI
Aug 29
Oct 7
Integrate with ERP to get organization pocket details & positions
Oct 24
Oct 28
Integrate with ERP APIs to maintain positions/budget
Oct 31
Nov 4
Specify test plan and test cases
Aug 29
Sep 23
Prepare test data for test cycles
Oct 24
Nov 4
Execute the maintenance test cases
Nov 7
Nov 18
Fix issues and data preparation
Nov 7
Nov 18
[Milestone]Conduct BAT on Maintaince service
Nov 18
Nov 18
Dry run with real business data prior go to production
Nov 21
Nov 25
Prepare production deployment
Nov 21
Nov 25
Release on production
Nov 25
Nov 25
There are no rows in this table