[Milestone] Distribute Yearly Budget
Jul 11
Nov 4
Define position creation behavior
Jul 11
Jul 31
PO | SA
Write user stories and acceptance criteria
Aug 10
Aug 18
PO
Design budget tracker solution
Aug 1
Aug 5
PO | SA
Maintain the solution integrity and behavior
Aug 22
Nov 4
PO | SA
[Phase] Develop the ERP budget tracker
Aug 8
Sep 30
Build distributed budget setup
Aug 8
Aug 12
ERP
Store distributed budget of each hiring type per sector
Aug 15
Aug 19
ERP
Submit distributed budget to ERP Budget setup
Aug 15
Aug 26
ESB | BE | FE
Build an APIs to retrieve planning lookups
Aug 22
Sep 2
ERP
Retrieve planning list of values
Sep 5
Sep 9
ESB | BE | FE
Build an API to calculate need cost per hiring type
Sep 5
Sep 9
ERP
Calculate the requested need cost
Sep 12
Sep 16
ESB | BE | FE
Develop alghoritm (BR) to validate the submitted plan
Sep 5
Sep 9
ERP
Build organization pockets structure “budget tracker”
Sep 12
Sep 30
ERP
Validate the saved draft/submitted plan
Sep 12
Sep 23
ESB | BE | FE
Show retrieved validation error message and enable edit actions
Sep 26
Oct 14
ESB | BE | FE
Refactor planning components, improve usability and performance
Aug 15
Sep 23
FE
Prepare test data for test cycles
Sep 12
Sep 23
QA | ERP
Execute system testing on budget distribution/planning
Sep 26
Oct 21
QA
Fix issues and data preparation
Sep 26
Oct 21
ERP | ESB | BE | FE
Specify test plan and test cases
Aug 22
Sep 30
QA
[Phase] Develop position auto creation services
Oct 3
Oct 21
Store planned vacant positions
Oct 3
Oct 14
ERP
Integrate with ERP to build new vacant positions/budget
Oct 17
Oct 21
ESB | BE | FE
Test the auto creation of budget/position
Oct 24
Nov 4
QA
Fix issues and data preparation
Oct 24
Nov 4
ERP | ESB | BE | FE
[Milestone]Conduct BAT on Distribution with budget
Nov 4
Nov 4
Dry run with real business data prior go to production
Nov 7
Nov 18
Prepare production deployment
Nov 21
Nov 25