[Phase] Demand Solution Envisioning
Mar 13
Mar 31
Finalize user stories and acceptance criteria
Mar 20
Mar 31
PO
Manage the definition of Sectors,Applicants, Approval Authority Users.
Mar 20
Mar 22
PO
Design subsumed process flow (GM to BP) and (BP to VP to Workforce)
Mar 13
Mar 31
3 Weeks
SA | PO | ERP | BE
Enhance Workforce Demand Experience
Mar 13
Mar 24
UX
[Phase] Identify Org. Needs
Apr 10
May 19
Develop the Applicant process
Apr 10
Apr 28
3 weeks
SA | PO | ERP | BE | FE
Plan and execute test scenarios and test cases
May 8
May 19
2 weeks
QA | ERP | BE | FE
Conduct BAT on Identify Org Needs
May 19
May 19
[Phase] Review associated Sectors Requests
May 15
Jun 16
Develop the HRBP process of sector’s Org needs
May 15
Jun 2
3 weeks
SA | PO | ERP | BE | FE
Plan and execute test scenarios and test cases
Jun 5
Jun 16
2 weeks
QA | ERP | BE | FE
Conduct BAT on Review Associated Sectors Needs
Jun 16
Jun 16
[Phase] Review Sector Budget Request
Jun 12
Jun 30
Develop the HRBP process of VP/CxO Sector needs
Jun 12
Jun 23
2 weeks
SA | PO | ERP | BE | FE
Plan and execute test scenarios and test cases
Jun 26
Jun 30
1 weeks
QA | ERP | BE | FE
Conduct BAT on Review Sector Budget Request
Jun 30
Jun 30
[Phase]Review Workforce Demand Budget Plan
Jul 3
Aug 11
Develop the HRBP process of all Sector needs
Jul 3
Jul 28
3 Weeks
SA | PO | ERP | BE | FE
Plan and execute test scenarios and test cases
Jul 31
Aug 11
2 weeks
QA | ERP | BE | FE
Conduct BAT on Review Workforce Demand Budget Plan
Aug 11
Aug 11
[Phase] Modify the Yearly Budget Distribution
Aug 7
Sep 8
Modify the budget plan to retreive approved sector demand as default
Aug 7
Aug 25
3 Weeks
SA | PO | ERP | BE | FE
Execute system testing on budget distribution/planning
Aug 28
Sep 8
2 Weeks
QA | ERP | BE | FE
Conduct BAT on Distribute Yearly Budget
Sep 8
Sep 8