Workstreams
Task
Status
Goals/Metrics/Status
Action Items
2
Mozenda Technology
To never allow the infrastructure constraints of Mozenda to be a blocker for bringing Dexi workloads to Mozenda.
Test solution to the max db connections issue on Master
2.1
Build a new data center
To increase stability of the Mozenda platform.
2.3
Expand data center with more database servers and job servers
(Added to scope since project start) To replace the WallE system for scraping Walmart with Mozenda.
No results from filter

Owned by Heather
#
Workstreams
Task
Status
Goals/Metrics/Status
Action Items
1
Communication
Keep as many accounts as possible by providing a great customer experience and tranisiton plans
Coming up wth a plan before reaching out. Need resources and plan for each customer
1.3
High Impact Account Plan
5 accounts - 5 in progress,
No results from filter

Owned by Scott
#
Workstreams
Task
Status
Goals/Metrics/Status
Action Items
1.1
Subscriptions
27 accounts (active subscriptions) -Ten in Progress, 17 still working to connect, 32 inactive, 2 canceled.
Met with 2 accounts (Both went well - setting up Mozenda accounts for both and they are going to test the software) / Sent 2 emails to all active accounts / have 2 more meetings set / Possibly 1 upsell in the works with Burt Processing $1,320 to $8,000 (Needs to rebuild 125 bots)
4.3
Subscription Account Plan
6.2
Review all Pricing Plans
Outlined general plan option for a monthly introductory plan, specs for the Corporate Individual / Corporate / Enterprise
6.3
Create New Mozenda Contracts
Reached out to Tom to get new letterhead for Mozenda. Talked with Bryan - Agreed to use the current terminology in the Dexi contracts with a few updates.
No results from filter

Owned by Mariah
#
Workstreams
Task
Status
Goals/Metrics/Status
Action Items
1.4
Hybrid
3/4 Accounts In Progress - Artnet transition is in progress - nearly completed. Confirmed Choice screening feasibility. Lock down resource to move forward. Communication will go out to Deutsche Bank this week.
Create MZ Self serve accounts, bot builds, inform clients/ tranining
5.1
Remove Workers
All inactive accounts have been removed. Will continue to remove workers as we complete the transition.
No results from filter

Owned by Alex
#
Workstreams
Task
Status
Goals/Metrics/Status
Action Items
1.5
Communication/Education/Documentation
Comparable Features doc complete! Will begin to share in onboarding emails and will begin to share with clients. Toni is working on Agent Template documentation.
4
Self-Serve Customer Migrations
See Customer Tracker for Stats. Feel comfortable moving to green once we have AI resources vetted and are moving forward with technical resources.
No results from filter