SALUS Product Roadmap

***Roadmap details and timelines are subject to change
Add New feature
PRODUCT FEATURES
1
Project
Feature
Start
End
Notes
Positions Required
FTE Equivalent
Roles
4
Roles (Phase One) - Design, Database and API Development, Market Research
10/1/2021
12/31/2021
Wire frames, UI/UX
Back end architecture and infrastructure work
Interview current clients
Interview industry leaders

Product Designer Backend Developer Product Manager Project Manager
15% 50% 10% 25%
Roles (Phase Two) - Backend Continued and Start Frontend
1/1/2022
3/31/2022
Start frontend development
Database scripting for backwards compatibility
Build out marketing content and communications
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
25% 25% 10% 25% 10% 15%
Roles (Phase Three) - Org Chart and Reporting Structure
4/1/2022
5/31/2022
Design UI/UX for org chart
Design data model for reporting structure
Build out API to manage reporting structure
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
15% 25% 5% 15% 5%
Roles (Phase Four) - Compliance
6/1/2022
8/31/2022
Build out compliance worker module
Notifications for workers out of compliances
Worker/Role Reporting dashboard
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
25% 25% 5% 15% 5% 10%
Subcontractor
2
Subcontractor Portal (Phase One) - Onboarding
1/1/2022
3/31/2022
Pre-qualification requests by contractor
Company Documents
Proof of insurance
Site Specific Documents
Streamlined invitation process
Enhanced compliance insight, filters etc (Prime contractor sites only)
Sites
Worker profile
Forms
Documents
Certificates

Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
50% 25% 5% 15% 0% 25%
Subcontractor Portal (Phase Two) - Reporting
3/28/2022
7/27/2022
Reporting
Sites
Workers
Forms
Certs
QR Codes
Site Specific
Asset
Sub Specific
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
50% 50% 5% 15% 0% 15%
Integrations
3
Power BI Connector (Business data analytics)
9/1/2021
10/15/2021
Build custom PowerBI adapter to be utilized by enterprise customers. This adapter will connect to our reporting data store to give clients access to per-processed data.
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
10% 0% 5% 10% 0% 0%
Integrations (Phase One) - Procore
1/1/2022
2/28/2022
Site sync
Worker sync
Link to dashboard
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
25% 0% 5% 10% 0% 0%
Integrations (Phase Two) - Procore
3/1/2022
4/30/2022
Subcontractor sync
Document sync
Reporting
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
25% 0% 5% 10% 0% 0%
Reporting
3
Reporting (Phase One) - Detailed Dashboards
9/1/2021
12/31/2021
Enhanced Feature Dashboards
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
50% 25% 10% 15% 0% 25%
Reporting (Phase Two) - Subcontractor and Compliance
1/1/2022
3/31/2022
Subcontractor Compliance reporting
Feature specific exporting
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
50% 25% 10% 15% 0% 25%
Reporting (Phase Three) - Custom Reports
4/1/2022
6/30/2022
Custom Reporting by feature
Customizable Reports per feature
Recurring reports
Exportable Reports, Excel, CSV and PDF
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
50% 25% 10% 15% 0% 25%
Analytics
3
Analytics (Phase One) - ML and AI
6/1/2022
9/30/2022
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
50% 25% 15% 25% 0% 25%
Analytics (Phase Two) - ML and AI
10/1/2022
12/31/2022
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
75% 50% 15% 25% 0% 25%
Analytics (Phase Three) - ML and AI
1/1/2023
3/31/2023
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
75% 50% 15% 25% 0% 25%
LMS
3
Learning Mgmt. System (Phase One) - Internal Company
9/1/2022
12/31/2022
Customizable training courses
Video and tests
Track progress / Pass Fail
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
50% 50% 15% 10% 0% 25%
Learning Mgmt. System (Phase Two) - Subcontractor
1/1/2023
3/31/2023
Enhanced orientations for subs / internal employees
Backend Developer Frontend Developer Product Manager Project Manager Product Marketing Product Designer
50% 25% 15% 10% 0% 15%

You can drag around the bars in this Gantt chat to update the timing and sequencing of your roadmap.
Gantt View
1
Roles
Roles (Phase One) - Design, Database and API Development, Market Research
Roles (Phase Two) - Backend Continued and Start Frontend
Roles (Phase Three) - Org Chart and Reporting Structure
Roles (Phase Four) - Compliance
Subcontractor
Integrations
Reporting
Analytics
LMS
Q3 2021
Q4 2021
Q1 2022
Q2 2022
Q3 2022
Q4 2022
Q1 2023
Q2 2023
Roles (Phase One) - Design, Database and API Development, Market Research
Roles (Phase Two) - Backend Continued and Start Frontend
Roles (Phase Three) - Org Chart and Reporting Structure
Roles (Phase Four) - Compliance
Subcontractor
2
Integrations
3
Reporting
3
Analytics
3
LMS
3