Below is the proposed timeline with key phases and milestones for the project. The timeline assumes development can start immediately and is an ideal scenario, subject to adjustment based on resource availability and any unforeseen complexities. Time estimates are given in weeks, and milestones mark the completion of major deliverables:
Phase 1: Requirements & Design
Phase 2: Prototype Scraper Development
Phase 3: Multi-site Scraper Implementation
Phase 4: Data Pipeline Integration
Phase 5: Deployment Setup
Phase 7: Launch & Handover
Apr 2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
May 2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Jun 2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Jul 2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Aug 2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Sep 2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Oct 2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Nov 2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Dec 2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Phase 1: Requirements & Design
Phase 2: Prototype Scraper Development
Phase 3: Multi-site Scraper Implementation
Phase 4: Data Pipeline Integration
Phase 5: Deployment Setup
Phase 7: Launch & Handover
View of High Level Timeline
Note on Timeline:
This schedule outlines roughly 2-3 months (10 weeks) of development. If more resources (developers) are available, some phases could be done in parallel – for instance, scrapers for different sites could be built simultaneously to shorten Phase 3. Conversely, if this is a single-developer project or if the client adds more requirements, the timeline might extend. Regular checkpoints with the stakeholders (at end of each phase) are included to ensure alignment and to accommodate feedback early (for example, after Phase 2 prototype, we may refine requirements before proceeding).
Each milestone delivers a tangible output (prototype, dataset, deployment, etc.), allowing AutoCompare to track progress. By Phase 7, the goal is to have a fully functioning, automated scraping platform running in production, with the team ready to maintain it.
Team Responsibility Matrix (RACI)