1. Project Requirement Gathering (2 weeks):
10/16/2023
14 days
Meetings with stakeholders. Documenting specifications. Finalizing the project scope. Complete project feature list and requirement gathering.
2. UI/UX Design Phase (4 weeks):
10/30/2023
30 days
Initial mockups and wireframes. Iterative feedback process. Complete UIUX design of the whole platform.
3. Development Phase (12 weeks):
11/30/2023
84 days
Week 1-3: Backend architecture and database design. Initialization of core services. Week 4-5: Frontend development for mobile app catering to females and males (profile creation, venue discovery, payments). Week 6-7: Development for the merchant web app (reservations, user interactions, offers). Week 8: Development of the admin dashboard with essential monitoring tools and user management. Week 9-12: Integration of all frontend and backend elements. Complete development of the frontend, backend and mobile app.
4. Testing Phase (2 weeks):
2/29/2024
14 days
Final testing and bug fixes. Ensuring the software works as intended and all bugs are fixed.
5. Deployment & Launch Phase (4 weeks)
3/14/2024
30 days
Deployment to app stores and production web hosting. On-call maintenance for 1 month to ensure everything is ok and any issues resolved. Complete development and deployment while ensure everything runs smoothly on deployment.