#r5
0
Marina View FSSD
Zay Aung
FSSD
Status
1
Not started
2
In-progress
3
At risk
4
Complete
5
There are no rows in this table
info
Keep track of each meeting topic in a new row, and add details in the notes column. Row order is based on the date, which can be changed in the table’s sort option.
Clear sample data
Agenda

Table 1
Updated on:
26-Jun-24
Column 3
Column 4
Column 5
Column 6
1st Submission
1st Submission 2
1st Submission 3
1st Submission 4
2nd Submission (Rev A)
2nd Submission (Rev A) 2
2nd Submission (Rev A) 3
2nd Submission (Rev A) 4
3rd Submission (Rev B)
3rd Submission (Rev B) 2
3rd Submission (Rev B) 3
3rd Submission (Rev B) 4
Summary
Summary 2
Summary 3
Summary 4
Summary 5
Column 24
Column 25
1
ATCC-RFA-ACMV-001
MV SYSTEM SCHMATIC DIAGRAM (ANNEX)
ACMV
NA
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
2
ATCC-RFA-ACMV-002
AC SYSTEM SCHMATIC DIAGRAM (ANNEX)
ACMV
NA
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
3
ATCC-RFA-ACMV-003
NOTES & LEGEND (ACMV)
ACMV
NA
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
4
ATCC-RFA-ACMV-004
1ST STOREY PLAN ACMV SYSTEM (ANNEX)
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
5
ATCC-RFA-ACMV-005
2ND STOREY PLAN ACMV SYSTEM (ANNEX)
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
6
ATCC-RFA-ACMV-006
3RD STOREY PLAN ACMV SYSTEM (ANNEX)
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
7
ATCC-RFA-ACMV-007
4TH STOREY PLAN ACMV SYSTEM (ANNEX)
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
8
ATCC-RFA-ACMV-008
5TH STOREY PLAN ACMV SYSTEM (ANNEX)
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
9
ATCC-RFA-ACMV-009
6TH STOREY PLAN ACMV SYSTEM (ANNEX)
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
10
ATCC-RFA-ACMV-010
ROOF PLAN ACMV SYSTEM (ANNEX)
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
11
ATCC-RFA-ACMV-011
1ST STOREY PLAN CARPARK VENTILATION SYSTEM
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
12
ATCC-RFA-ACMV-012
2nd STOREY PLAN CARPARK VENTILATION SYSTEM
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
13
ATCC-RFA-ACMV-013
3rd STOREY PLAN CARPARK VENTILATION SYSTEM
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
14
ATCC-RFA-ACMV-014
4th STOREY PLAN CARPARK VENTILATION SYSTEM
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
15
ATCC-RFA-ACMV-015
5th STOREY PLAN CARPARK VENTILATION SYSTEM
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
16
ATCC-RFA-ACMV-016
TOILET MV LAYOUT
ACMV
4 Months
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
17
ATCC-RFA-ACMV-017
STANDARD DETAILS 1
ACMV
NA
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
18
ATCC-RFA-ACMV-018
STANDARD DETAILS 2
ACMV
NA
21/Dec/23
28.Nov.2023
05.Jan.2024
Waiting for response
19
ATCC-RFA-ACMV-MOS-001
Method Statement of ACMV Installation
ACMV
NA
24.Nov.2023
07.dec.2023
01.dec.2023
Resubmission required
20
ATCC-RFA-ACMV-MOCKUP-001
Ducting Installation - Mock Up at 1st Storey
ACMV
NA
Mock Up Installation Schedule base on the site progress
21
ATCC-RFA-ACMV-MOCKUP-002
AC Installation - Mock Up at 6th Storey
ACMV
NA
Mock Up Installation Schedule base on the site progress
22
ATCC-RFAM-ACMV-001
Pre-Insulated Duct
ACMV
3 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
RNR
23
ATCC-RFAM-ACMV-002
Duct Insulation - Internal
ACMV
3 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
Approved with comments
24
ATCC-RFAM-ACMV-003
Duct Insulation - External
ACMV
3 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
RNR
25
ATCC-RFAM-ACMV-004
Duct Work Sealant
ACMV
2 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
Approved with comments
26
ATCC-RFAM-ACMV-005
Gasket for Duct Work
ACMV
2 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
Approved with comments
27
ATCC-RFAM-ACMV-006
Flexible Duct
ACMV
2 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
RNR
28
ATCC-RFAM-ACMV-007
Thermofoil
ACMV
2 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
RNR
29
ATCC-RFAM-ACMV-008
Aluminium Foil Tape
ACMV
2 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
RNR
30
ATCC-RFAM-ACMV-009
Adension of Glasswool
ACMV
2 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
Approved with comments
31
ATCC-RFAM-ACMV-010
Refrigerant Copper Pipe
ACMV
3 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
Approved with comments
32
ATCC-RFAM-ACMV-011
Insulation for Copper Pipes & Drain Pipes
ACMV
2 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
Approved with comments
33
ATCC-RFAM-ACMV-012
Fire Rated Board
ACMV
3 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
Approved with comments
34
ATCC-RFAM-ACMV-013
Drop In Anchor & Expansion Bolt
ACMV
2 Weeks
30/Dec/23
08.12.2023
21.12.2023
12.01.2024
Approved with comments
35
ATCC-RFAM-ACMV-014
G.I Duct Material
ACMV
3 Weeks
30/Dec/23
14.Dec.2023
27.Dec.2023
Waiting for response
36
ATCC-RFAM-ACMV-015
uPVC Drain Pipes & Accessories
ACMV
2 Weeks
30/Dec/23
14.Dec.2023
27.Dec.2023
Waiting for response
37
ATCC-RFAM-ACMV-016
Mechanical Ventilation Fans
ACMV
3 Months
11.Jan.2024
29.Dec.2023
11.Jan.2024
Waiting for response
38
ATCC-RFAM-ACMV-017
Carpark Jet Fans
ACMV
2 Months
11.Jan.2024
29.Dec.2023
11.Jan.2024
Waiting for response
39
ATCC-RFAM-ACMV-018
VRV System (FCU & CU)
ACMV
4 Months
11.Jan.2024
29.Dec.2023
11.Jan.2024
Waiting for response
40
ATCC-RFAM-ACMV-019
G.I Trunking & Tray
ACMV
3 Weeks
17/Mar/24
8.Jan.2024
30.Jan.2024
Waiting for response
41
ATCC-RFAM-ACMV-020
G.I Conduit, Flexible & Accessaries
ACMV
3 Weeks
17/Mar/24
8.Jan.2024
30.Jan.2024
Waiting for response
42
ATCC-RFAM-ACMV-021
Grilles, Diffuser & Louver
ACMV
3 Weeks
17/Mar/24
43
ATCC-RFAM-ACMV-022
Fire Damper, VCD & NRD
ACMV
3 Weeks
17/Mar/24