Requirements
scrappy’s bucket list ? if we have time...
are the people who hold the events going to go to our site in order to post events if owl life integration is not easy
register to ksu email
no authentication
must have:
capture event information
nice to have:
way to pull data out of data base
SPRINT 1: Requirements & Design (Weeks 1–4)
Project Plan (SCP-Form02) Requirements Specification Document SDS: Sections 1–3 (Intro, System Overview, Architecture) Weekly Progress Reports (Form03)
SPRINT 2: MVP Development (Weeks 5–10)
Frontend login, dashboard, event viewer Backend for admin portal, event ingestion (RSS feed) Admin: upload/edit events, milestones Check-in button with logging Weekly Reports + Midterm Demo Test Plan (Test Doc Sections 1.1–1.5) SDS: Sections 4–6 (Detailed Design, DB, UI/UX Design)
SPRINT 3: Finalization & Deployment (Weeks 11–15)
Final product with all milestone logic and badges Fully functioning admin dashboard Automated certificates/notifications Gamification complete (progress bars, badges) Test Results (Section 2 & 3 of Test Doc) Final Presentation (Department showcase) Poster Presentation (C-Day) Final Package (code, all documents, meeting logs) Project Acceptance Form (SCP-Form04)