Project Management

icon picker
Determine Project Progress & Performance

The Project is on Schedule.
The Project is under Budget.

Earned Value Measurements

What is current budget at completion (BAC): $105,430.00
Determine your current project earned value (EV): $15,595.00
Determine analysis phase actual cost (AC): $14,866.00
Determine analysis phase planned value (PV): $15,595.00
Determine estimate to complete (ETC):$85,635.60
Determine estimate at complete (EAC): $100,501.60
Determine variance at complete (VAC): $4,928.40
Determine the current cost variance (CV): $729.00
Determine cost performance index (CPI): 1.04904
Determine schedule performance index (SPI): 1.00
What is your current schedule variance (SV): $0.00
Phases Progress & Performance
0

Earned Value Formulas

AC: Total actual cost incurred for the current period of performance
BAC: Total project budget
CPI: EV divided by the AC
CV: EV minus the AC
EAC: BAC divided by the CPI
ETC: EAC minus the AC
EV: Percent of completed work times the BAC (budget at completion)
PV: Percent complete times the total project budget
SPI: EV divided by the PV
SV: EV minus the PV
VAC: BAC minus the EAC
Budget/WBS Timeline/Gantt View
0

Want to print your doc?
This is not the way.
Try clicking the ⋯ next to your doc name or using a keyboard shortcut (
CtrlP
) instead.