Sprint Report - Denmark (02/05/24 - 02/16/24)

Platform Squad Sprint Summary

Completed Sprint: Denmark (02/05/24 - 02/16/24)


Estimated Time: 131hrs
Actual Time: 107hrs
Unplanned Work Brought In Mid-Sprint: 3hrs

Key Initiative Focus Items:
50% complete with Phase 3 of Kount. Have 6 more Kount tasks. Plan to have Kount live by mid-march
Worked through the implementation of alerts being sent to Kustomer
Logic to successfully refund subscription orders
Met with Jacques to go over the data deletion setup.
Delayed due to an unknown LOE in regards to custom scripts for pixel deletion. Effort to be confirmed on 2/21 EOD
We completed the API Decision Gateway task and deployed on x date along with the event queuing

Squad Related Items:
2 tasks were added mid-sprint:
Had a large cross-functional meeting involving OPS, SITE, Platform, and QA to create a QA end-to-end testing plan for . QA begins 2/20 and go through 2/27. We are planning to have this live 2/28
Risks:
Finalizing requirements for Ketch

Upcoming Sprint: Egypt (02/19/24 - 03/1/24)

Estimated Hours: 138hrs
Sprint Focus Items:
US Order Distribution Tool
Ketch Mongo DB Data Deletion
Kount Ethoca Alerts

Site Squad Sprint Summary

Completed Sprint: Denmark (02/05/24 - 02/16/24)

Estimated Time: 156hrs
Actual Time: 150hrs
Unplanned Work Brought In Mid-Sprint: 5hrs

Key Initiative Focus Items:
Launched test on 2/13. Currently waiting for feedback based on data.
Completed [Rudderstack]: Ketch integration action plan. Have now setup all pixels.
Finished implementation and preparing for launch.
Additional Tasks:
ABLR Updates
Adding product data to Strapi
Yotpo Order API
Turn off shipping for specific postal codes in Spain

Upcoming Sprint: Egypt (02/19/24 - 03/1/24)

Estimated Time: 180 hrs
Sprint Focus Items:
Site Experience: PDP - Implementing PDP for the test
Site Experience: Nav/CLP - Implementing Banner component updates
LM 4.0 Pro, LM 3.0 Plus, SS Blade 2.0] [US,CA] - Beginning implementation
Releasing Handyman Replacement Blades
Adding product data to Strapi
Risks:
Getting feedback from the Nav/CLP test could impact priorities
Requirements for next Site Experience Components are in the works
Had to push back the launch of the Site Experience PDP test after discussing needing to have the Nav and CLP in production before the PDP test can begin. Test is being moved to July.

OPS Squad Sprint Summary

Completed Sprint: Denmark (02/05/24 - 02/16/24)

Estimated Time: 102 hrs
Actual Time: 108 hrs
Unplanned Work Brought In Mid-Sprint: 4hrs

Key Initiative Focus Items:
Focus was on cross-sqaud development planning, FSD scoping, & backend + UX/UI design.
Squad Related Items:
Mock Service development w/ support from SRE to deploy to staging
CX Order Resubmission Tool development w/ support from SRE to establish a portal and service connection
Automation of Maersk Address Corrections w/ support from SRE to setup and test teams client
FSD Rejected Flow & Seko Service Updates

Upcoming Sprint: Egypt (02/19/24 - 03/1/24)

Estimated Time: 102 hrs
Sprint Focus Items:
Development of US Distribution Tool
Risks:
Resources are at max capacity leaving little wiggle room for unknowns to pop up without delaying the US Distribution Tool timeline.