Tasks (in priority order): 1. Model lower ground floor/foundations 2. Create immediate garden area around house 3. Add swimming pool if time permits
Technical Details: - Use existing class system that Philip has imported - Work from December 24th architect's PDFs - Lower ground floor plan needs loading and scaling - Source file is in shared folder "Coolshannah, Bermuda | February 2025 | WIP"
Project Status: - Philip has completed: roofs, upper ground and first floor - He's currently working on ground and first floor modifications
Timeline: - Deadline: Wednesday, February 12th, 2025 - Client presentation: Thursday, February 13th, 2025 - Suggested timeframe: 30 hours total
The critical aspects are: - House completion takes priority over garden - Swimming pool is more important than full garden extent - Coordination needed as Philip works simultaneously on other floors

To-do list

Pre-modeling Tasks
Load December 24th architect's PDFs
Scale the lower ground floor plan
Review existing class system implementation
Primary Modeling
Lower ground floor/foundations modeling
Secondary Modeling
Immediate garden area
Optional Modeling
Swimming pool (4h)