HTC
Home
HTC Project schedule.
HTC Cash flow
Back-end
More
Share
Explore
Back-end
Weekly updates.
📤 Send Email Update
Status
The status for this project is:
😃 On Track
as of
4/22/2020
Focus Areas
We'll want to really pay attention to
14
pending decisions we need to confirm from client over the next few weeks as that will be the driving force behind this entire plan! Here's a high-level of what to focus on:
Search
Tasks Completed Last Week
Task Starting This Week
Tasks Ending This Week
1
@
trial
@
Trial 2
@
OHWT, Lift slab, etc. RCC
@
Blockwork
@
Electrical conduits
@
Internal Plaster
@
UGWT
@
Backside ramp slab
@
Lift Girder fixing as required.
@
External texture work & Paint.
@
External plaster
@
Internal Plumbing
@
Granite frames
@
External Plumbing
@
Waterproofing + PCC (bathrooms) & (Common toilet)
@
3rd basement plaster.
@
Electric cable tray & lighting
@
Trench & Sump
@
Dado in bathrooms
@
Fire Sprinklers & vertical lines
@
Floor finish
@
Lift Order & Delivery
@
Terrace water proofing.
@
Facade work
@
Flooring in shops, offices, foyers and granite cladding.
@
False ceiling in passages.
@
Final coat paint
@
Transformer, GEB meter, earthing, etc.
@
Office doors, shop glasss doors, windows & vents.
@
Lift Installation
@
Internal wiring & MCB
@
Common Amenities, Exterior Work & Landscaping, compound wall, granite work, planters, etc.
@
Txture work in passages.
@
Putty final coat
@
Stair railing
@
CP, Sanitary & Housekeeping
@
Signboards/ Nameplate
@
External lighting work.
@
trial
@
Trial 2
@
Blockwork
@
Electrical conduits
@
Granite frames
@
Internal Plaster
@
Trench & Sump
@
OHWT, Lift slab, etc. RCC
@
3rd basement plaster.
@
Internal Plumbing
@
External plaster
@
External Plumbing
@
Dado in bathrooms
@
Lift Girder fixing as required.
@
UGWT
@
Backside ramp slab
@
External texture work & Paint.
@
Electric cable tray & lighting
@
Waterproofing + PCC (bathrooms) & (Common toilet)
@
Terrace water proofing.
@
Floor finish
@
Fire Sprinklers & vertical lines
@
False ceiling in passages.
@
Lift Order & Delivery
@
Final coat paint
@
Office doors, shop glasss doors, windows & vents.
@
Internal wiring & MCB
@
Flooring in shops, offices, foyers and granite cladding.
@
Txture work in passages.
@
Putty final coat
@
Common Amenities, Exterior Work & Landscaping, compound wall, granite work, planters, etc.
@
Signboards/ Nameplate
@
Transformer, GEB meter, earthing, etc.
@
Facade work
@
Stair railing
@
Lift Installation
@
CP, Sanitary & Housekeeping
@
External lighting work.
There are no rows in this table
Have a great week ahead 👍
Thanks,
Nipul Thakker 😊
Status
Focus Areas
Have a great week ahead 👍
Related Docs
Two-way writeups: Coda’s secret to shipping fast
Lane Shackleton
Gokul's S.P.A.D.E. Toolkit
Gokul Rajaram
The Notion User's Guide to Coda (2022 Edition)
Ben Parker
Coda's ritual of innovation: How we created (almost) 100 Packs in one day
Oliver Heckmann
How to build tasks dependencies with durations in Google Sheets, ClickUp, Monday, Wrike, SmartSheet, Notion, and Coda
Al Chen
Team Retrospective
Glenn Jaume
Rethinking Google's Famous LaunchCal
Shiva Rajaraman
Shishir's Guide to Distributed Teams
Shishir Mehrotra
Project Roadmap Guide [+ Resource Utilization Template]
Al Chen
Project plan
Al Chen
Why your company needs rituals: A Masters of Scale companion doc
Shishir Mehrotra
How Appetiser grew from $2M to $8M in 2 years with Coda
Coda
Tally + Coda
Marie Martens
Automate the $*%! out of user research so it's not painful — and actually happens
Punit Shah
Small Business CRM and Project Tracker
Maria Marquis
Related Categories
Project management
Want to print your doc?
This is not the way.
Try clicking the ⋯ next to your doc name or using a keyboard shortcut (
Ctrl
P
) instead.