Skip to content
Back-end

Weekly updates.


📤 Send Email Update

Status

The status for this project is:
😃 On Track
as of
4/22/2020

Focus Areas

We'll want to really pay attention to
14
pending decisions we need to confirm from client over the next few weeks as that will be the driving force behind this entire plan! Here's a high-level of what to focus on:

Tasks Completed Last Week
Task Starting This Week
Tasks Ending This Week
1

@trial
@Trial 2
@OHWT, Lift slab, etc. RCC
@Blockwork
@Electrical conduits
@Internal Plaster
@UGWT
@Backside ramp slab
@Lift Girder fixing as required.
@External texture work & Paint.
@External plaster
@Internal Plumbing
@Granite frames
@External Plumbing
@Waterproofing + PCC (bathrooms) & (Common toilet)
@3rd basement plaster.
@Electric cable tray & lighting
@Trench & Sump
@Dado in bathrooms
@Fire Sprinklers & vertical lines
@Floor finish
@Lift Order & Delivery
@Terrace water proofing.
@Facade work
@Flooring in shops, offices, foyers and granite cladding.
@False ceiling in passages.
@Final coat paint
@Transformer, GEB meter, earthing, etc.
@Office doors, shop glasss doors, windows & vents.
@Lift Installation
@Internal wiring & MCB
@Common Amenities, Exterior Work & Landscaping, compound wall, granite work, planters, etc.
@Txture work in passages.
@Putty final coat
@Stair railing
@CP, Sanitary & Housekeeping
@Signboards/ Nameplate
@External lighting work.
@trial
@Trial 2
@Blockwork
@Electrical conduits
@Granite frames
@Internal Plaster
@Trench & Sump
@OHWT, Lift slab, etc. RCC
@3rd basement plaster.
@Internal Plumbing
@External plaster
@External Plumbing
@Dado in bathrooms
@Lift Girder fixing as required.
@UGWT
@Backside ramp slab
@External texture work & Paint.
@Electric cable tray & lighting
@Waterproofing + PCC (bathrooms) & (Common toilet)
@Terrace water proofing.
@Floor finish
@Fire Sprinklers & vertical lines
@False ceiling in passages.
@Lift Order & Delivery
@Final coat paint
@Office doors, shop glasss doors, windows & vents.
@Internal wiring & MCB
@Flooring in shops, offices, foyers and granite cladding.
@Txture work in passages.
@Putty final coat
@Common Amenities, Exterior Work & Landscaping, compound wall, granite work, planters, etc.
@Signboards/ Nameplate
@Transformer, GEB meter, earthing, etc.
@Facade work
@Stair railing
@Lift Installation
@CP, Sanitary & Housekeeping
@External lighting work.
There are no rows in this table


Have a great week ahead 👍


Thanks,

Nipul Thakker 😊

Want to print your doc?
This is not the way.
Try clicking the ⋯ next to your doc name or using a keyboard shortcut (
CtrlP
) instead.