HTC Project schedule.
HTC Cash flow
Back-end
More
Share
Explore
Back-end
Weekly updates.
📤 Send Email Update
Status
The status for this project is:
😃 On Track
as of
12/7/2022
Focus Areas
We'll want to really pay attention to
14
pending decisions we need to confirm from client over the next few weeks as that will be the driving force behind this entire plan! Here's a high-level of what to focus on:
Tasks Completed Last Week
Task Starting This Week
Tasks Ending This Week
Tasks Completed Last Week
Task Starting This Week
Tasks Ending This Week
1
@
OHWT, Lift slab, etc. RCC
@
Blockwork
@
Electrical conduits
@
External plaster
@
External texture work & Paint.
@
External Plumbing
@
Internal Plaster
@
Waterproofing + PCC (bathrooms) & (Common toilet)
@
Terrace water proofing.
@
Internal Plumbing
@
Granite frames
@
Dado in bathrooms
@
Flooring in shops, offices, foyers and granite cladding.
@
Office doors, shop glasss doors, windows & vents.
@
Facade work
@
Internal wiring & MCB
@
Putty final coat
@
CP, Sanitary & Housekeeping
@
UGWT
@
Backside ramp slab
@
Electric cable tray & lighting
@
Fire Sprinklers & vertical lines
@
Trench & Sump
@
3rd basement plaster.
@
Floor finish
@
Final coat paint
@
Lift Girder fixing as required.
@
Lift Order & Delivery
@
Lift Installation
@
Common Amenities, Exterior Work & Landscaping, compound wall, granite work, planters, etc.
@
Transformer, GEB meter, earthing, etc.
@
False ceiling in passages.
@
Txture work in passages.
@
External lighting work.
@
Signboards/ Nameplate
@
Stair railing
@
trial
@
Trial 2
@
OHWT, Lift slab, etc. RCC
@
Blockwork
@
Electrical conduits
@
External plaster
@
External texture work & Paint.
@
External Plumbing
@
Internal Plaster
@
Waterproofing + PCC (bathrooms) & (Common toilet)
@
Terrace water proofing.
@
Internal Plumbing
@
Granite frames
@
Dado in bathrooms
@
Flooring in shops, offices, foyers and granite cladding.
@
Office doors, shop glasss doors, windows & vents.
@
Facade work
@
Internal wiring & MCB
@
Putty final coat
@
CP, Sanitary & Housekeeping
@
UGWT
@
Backside ramp slab
@
Electric cable tray & lighting
@
Fire Sprinklers & vertical lines
@
Trench & Sump
@
3rd basement plaster.
@
Floor finish
@
Final coat paint
@
Lift Girder fixing as required.
@
Lift Order & Delivery
@
Lift Installation
@
Common Amenities, Exterior Work & Landscaping, compound wall, granite work, planters, etc.
@
Transformer, GEB meter, earthing, etc.
@
False ceiling in passages.
@
Txture work in passages.
@
External lighting work.
@
Signboards/ Nameplate
@
Stair railing
@
trial
@
Trial 2
There are no rows in this table
Have a great week ahead 👍
Thanks,
Nipul Thakker 😊
📤 Send Email Update
Status
Focus Areas
Have a great week ahead 👍