Skip to content
Back-end

icon picker
Weekly updates.


📤 Send Email Update

Status

The status for this project is:
😃 On Track
as of
12/7/2022

Focus Areas

We'll want to really pay attention to
14
pending decisions we need to confirm from client over the next few weeks as that will be the driving force behind this entire plan! Here's a high-level of what to focus on:
Tasks Completed Last Week
Task Starting This Week
Tasks Ending This Week
1

@OHWT, Lift slab, etc. RCC
@Blockwork
@Electrical conduits
@External plaster
@External texture work & Paint.
@External Plumbing
@Internal Plaster
@Waterproofing + PCC (bathrooms) & (Common toilet)
@Terrace water proofing.
@Internal Plumbing
@Granite frames
@Dado in bathrooms
@Flooring in shops, offices, foyers and granite cladding.
@Office doors, shop glasss doors, windows & vents.
@Facade work
@Internal wiring & MCB
@Putty final coat
@CP, Sanitary & Housekeeping
@UGWT
@Backside ramp slab
@Electric cable tray & lighting
@Fire Sprinklers & vertical lines
@Trench & Sump
@3rd basement plaster.
@Floor finish
@Final coat paint
@Lift Girder fixing as required.
@Lift Order & Delivery
@Lift Installation
@Common Amenities, Exterior Work & Landscaping, compound wall, granite work, planters, etc.
@Transformer, GEB meter, earthing, etc.
@False ceiling in passages.
@Txture work in passages.
@External lighting work.
@Signboards/ Nameplate
@Stair railing
@trial
@Trial 2
@OHWT, Lift slab, etc. RCC
@Blockwork
@Electrical conduits
@External plaster
@External texture work & Paint.
@External Plumbing
@Internal Plaster
@Waterproofing + PCC (bathrooms) & (Common toilet)
@Terrace water proofing.
@Internal Plumbing
@Granite frames
@Dado in bathrooms
@Flooring in shops, offices, foyers and granite cladding.
@Office doors, shop glasss doors, windows & vents.
@Facade work
@Internal wiring & MCB
@Putty final coat
@CP, Sanitary & Housekeeping
@UGWT
@Backside ramp slab
@Electric cable tray & lighting
@Fire Sprinklers & vertical lines
@Trench & Sump
@3rd basement plaster.
@Floor finish
@Final coat paint
@Lift Girder fixing as required.
@Lift Order & Delivery
@Lift Installation
@Common Amenities, Exterior Work & Landscaping, compound wall, granite work, planters, etc.
@Transformer, GEB meter, earthing, etc.
@False ceiling in passages.
@Txture work in passages.
@External lighting work.
@Signboards/ Nameplate
@Stair railing
@trial
@Trial 2
There are no rows in this table


Have a great week ahead 👍


Thanks,
Nipul Thakker 😊

Want to print your doc?
This is not the way.
Try clicking the ⋯ next to your doc name or using a keyboard shortcut (
CtrlP
) instead.