icon picker
HTC Project schedule.

Assuming 💭 work starts from 20th May.


We have completed
0
tasks so far, we still have
39
total tasks to achieve target. 🏇

Target completion date is
19/09/2020
, we have
1417 days ago
to close the project. 🎡

Progress:
Completed
Incomplete
(
0
% of tasks completed so far )

Add New Task
Task list
1
✔️
Assignee
Task Description
Phase of task
Status as on date - 21/03/2020 (since lockdown)
Remarks
Budgeted Start date
Budgeted End date
Effort Days
Mobilization time
Pending decision timeline
Actual effort days
Actual start date
Actual end date
1
NT
Nipul Thakker
OHWT, Lift slab, etc. RCC
Top roof F
OHWT slab steel binding, Lift pardi then slab.
Dates shall vary as per contractor's manpower availability after lockdown completion.
20/05/2020
09/06/2020
20 days
20 days
20/05/2020
09/06/2020
2
NT
Nipul Thakker
Blockwork
6th F
15% complete, Supply of blocks is crucial and date may vary as per availability.
20/05/2020
29/05/2020
9 days
9 days
20/05/2020
29/05/2020
3
NT
Nipul Thakker
Electrical conduits
5th F
6th F
5th, 6th floor
20/05/2020
30/05/2020
10 days
10 days
20/05/2020
30/05/2020
4
NT
Nipul Thakker
External plaster
ALL F
Front & Left side complete
Back side and right side plaster pending. Activity aligned after block work.
25/05/2020
14/06/2020
20 days
20 days
25/05/2020
14/06/2020
5
External texture work & Paint.
ALL F
Two sides available BUT activity ON HOLD from client.
Decision yet to be received from client. Activity aligned after external plaster.
22/05/2020
21/06/2020
30 days
7 days
15/05/2020
30 days
22/05/2020
21/06/2020
6
External Plumbing
GF
Vertical line 30% complete horizontal not started yet
Activity aligned after external plaster.
30/05/2020
14/06/2020
15 days
15 days
30/05/2020
14/06/2020
7
Internal Plaster
5th F
6th F
5th, 6th floor remaining
Activity aligned after block work.
20/05/2020
03/06/2020
14 days
14 days
20/05/2020
03/06/2020
8
Electric Floor Conduits
ALL F
N/A
Activity not to be executed as per client's instruction.
9
Waterproofing + PCC (bathrooms) & (Common toilet)
ALL F
12/36 completed
30/05/2020
26/06/2020
27 days
27 days
30/05/2020
26/06/2020
10
Terrace water proofing.
Roof F
Activity aligned after a week from OHWT slab casting.
16/06/2020
26/06/2020
10 days
10 days
16/06/2020
26/06/2020
11
Internal Plumbing
5th F
6th F
completed till 4th floor
Activity aligned after internal plaster.
28/05/2020
11/06/2020
14 days
14 days
28/05/2020
11/06/2020
12
Granite frames
5th F
6th F
completed till 4th floor
29/05/2020
02/06/2020
4 days
4 days
29/05/2020
02/06/2020
13
Dado in bathrooms
5th F
6th F
completed till 4th floor
Activity aligned after internal plaster.
04/06/2020
14/06/2020
10 days
10 days
04/06/2020
14/06/2020
14
Flooring in shops, offices, foyers and granite cladding.
ALL F
Fronts available but ON HOLD from client.
After completion of external texture work.
26/06/2020
13/08/2020
48 days
20 days
06/06/2020
48 days
26/06/2020
13/08/2020
15
Office doors, shop glasss doors, windows & vents.
ALL F
Work front available BUT agency not yet finalized by client.
Activity aligned after flooring is completed.
09/07/2020
30/07/2020
21 days
30 days
09/06/2020
21 days
09/07/2020
30/07/2020
16
Facade work
ALL F
Work front available BUT agency not yet finalized by client.
Activity aligned after external texture.
21/06/2020
04/09/2020
75 days
30 days
22/05/2020
75 days
21/06/2020
04/09/2020
17
Internal wiring & MCB
ALL F
on hold from client
Activity aligned after doors are fixed.
30/07/2020
09/08/2020
10 days
7 days
23/07/2020
10 days
30/07/2020
09/08/2020
18
Putty final coat
ALL F
Activity aligned after internal electrical work. Putty final coat to be done before possession, each floor will take 3 days
09/08/2020
27/08/2020
18 days
18 days
09/08/2020
27/08/2020
19
CP, Sanitary & Housekeeping
ALL F
Activity aligned after completion of final coat of putty.
27/08/2020
11/09/2020
15 days
15 days
27/08/2020
11/09/2020
20
UGWT
GF
Pardi steel complete
20/05/2020
19/06/2020
30 days
30 days
20/05/2020
19/06/2020
21
Backside ramp slab
Basement
Complete
Structural design as per client (half protion) and RCC portion as per Structural drawings.
20/05/2020
19/06/2020
30 days
30 days
20/05/2020
19/06/2020
22
Electric cable tray & lighting
Basement
ON HOLD from client
Work front available from 01/03/2020.
31/05/2020
25/06/2020
25 days
7 days
24/05/2020
25 days
31/05/2020
25/06/2020
23
Fire Sprinklers & vertical lines
Basement
Agency not finalized yet
Work front available from 01/03/2020.
09/06/2020
04/07/2020
25 days
15 days
25/05/2020
25 days
09/06/2020
04/07/2020
24
Trench & Sump
Basement
ON HOLD from client
Work front available from 01/03/2020.
03/06/2020
08/06/2020
5 days
10 days
24/05/2020
5 days
03/06/2020
08/06/2020
25
3rd basement plaster.
Basement
1 wall remaining overall complete
30/05/2020
09/06/2020
10 days
10 days
30/05/2020
09/06/2020
26
Floor finish
Basement
2nd basement complete, 1 st & 3rd basement remaining
10/06/2020
30/06/2020
20 days
20 days
10/06/2020
30/06/2020
27
Final coat paint
Basement
Not finalized yet
01/07/2020
26/07/2020
25 days
25 days
01/07/2020
26/07/2020
28
Lift Girder fixing as required.
Lift
Agency not finalized yet
No approval yet
20/05/2020
14/06/2020
25 days
5 days
15/05/2020
25 days
20/05/2020
14/06/2020
29
Lift Order & Delivery
Lift
14/06/2020
24/07/2020
40 days
40 days
14/06/2020
24/07/2020
30
Lift Installation
Lift
25/07/2020
08/09/2020
45 days
45 days
25/07/2020
08/09/2020
31
Common Amenities, Exterior Work & Landscaping, compound wall, granite work, planters, etc.
GF
Front steps, Passage masonary RCC work complete.
30/07/2020
29/08/2020
30 days
30 days
30/07/2020
29/08/2020
32
Transformer, GEB meter, earthing, etc.
GF
on hold from client.
After completing UGWT & its floor finish with paver work/road work.
04/07/2020
02/09/2020
60 days
30 days
04/06/2020
60 days
04/07/2020
02/09/2020
33
False ceiling in passages.
ALL F
Agency not finalized yet
After completion of terrace water proofing.
26/06/2020
21/07/2020
25 days
20 days
06/06/2020
25 days
26/06/2020
21/07/2020
34
Txture work in passages.
ALL F
Not finalized yet
After completion of flooring work
30/07/2020
14/08/2020
15 days
15 days
30/07/2020
14/08/2020
35
External lighting work.
ALL F
Not finalized yet
No agency to be hired as per client's decision. PMC working for approvals & options with help of vendor.
04/09/2020
19/09/2020
15 days
30 days
05/08/2020
15 days
04/09/2020
19/09/2020
36
Signboards/ Nameplate
ALL F
Not finalized yet
Activity aligned after final putty is completed.
27/08/2020
30/08/2020
3 days
30 days
28/07/2020
3 days
27/08/2020
30/08/2020
37
Stair railing
ALL F
Agency not finalized yet
Activity aligned with flooring
16/08/2020
05/09/2020
20 days
30 days
17/07/2020
20 days
16/08/2020
05/09/2020
38
trial
19/04/2020
23/04/2020
4 days
4 days
19/04/2020
23/04/2020
39
Trial 2
ALL F
NA
20/04/2020
25/04/2020
5 days
5 days
20/04/2020
25/04/2020
There are no rows in this table
38
Count

Want to print your doc?
This is not the way.
Try clicking the ⋯ next to your doc name or using a keyboard shortcut (
CtrlP
) instead.