HTC Project schedule.

Assuming 💭 work starts from 20th May.


We have completed
0
tasks so far, we still have
39
total tasks to achieve target. 🏇

Target completion date is
19/09/2020
, we have
1788 days ago
to close the project. 🎡

Progress:
Completed
Incomplete
(
0
% of tasks completed so far )

Add New Task
Task list
✔️
Assignee
Task Description
Phase of task
Status as on date - 21/03/2020 (since lockdown)
Remarks
Budgeted Start date
Budgeted End date
Effort Days
Mobilization time
Pending decision timeline
Actual effort days
Actual start date
Actual end date
OHWT, Lift slab, etc. RCC
OHWT slab steel binding, Lift pardi then slab.
Dates shall vary as per contractor's manpower availability after lockdown completion.
20/05/2020
09/06/2020
20 days
20 days
20/05/2020
09/06/2020
Blockwork
15% complete, Supply of blocks is crucial and date may vary as per availability.
20/05/2020
29/05/2020
9 days
9 days
20/05/2020
29/05/2020
Electrical conduits
5th, 6th floor
20/05/2020
30/05/2020
10 days
10 days
20/05/2020
30/05/2020
External plaster
Front & Left side complete
Back side and right side plaster pending. Activity aligned after block work.
25/05/2020
14/06/2020
20 days
20 days
25/05/2020
14/06/2020
External texture work & Paint.
Two sides available BUT activity ON HOLD from client.
Decision yet to be received from client. Activity aligned after external plaster.
22/05/2020
21/06/2020
30 days
7 days
15/05/2020
30 days
22/05/2020
21/06/2020
External Plumbing
Vertical line 30% complete horizontal not started yet
Activity aligned after external plaster.
30/05/2020
14/06/2020
15 days
15 days
30/05/2020
14/06/2020
Internal Plaster
5th, 6th floor remaining
Activity aligned after block work.
20/05/2020
03/06/2020
14 days
14 days
20/05/2020
03/06/2020
Electric Floor Conduits
N/A
Activity not to be executed as per client's instruction.
Waterproofing + PCC (bathrooms) & (Common toilet)
12/36 completed
30/05/2020
26/06/2020
27 days
27 days
30/05/2020
26/06/2020
Terrace water proofing.
Activity aligned after a week from OHWT slab casting.
16/06/2020
26/06/2020
10 days
10 days
16/06/2020
26/06/2020
Internal Plumbing
completed till 4th floor
Activity aligned after internal plaster.
28/05/2020
11/06/2020
14 days
14 days
28/05/2020
11/06/2020
Granite frames
completed till 4th floor
29/05/2020
02/06/2020
4 days
4 days
29/05/2020
02/06/2020
Dado in bathrooms
completed till 4th floor
Activity aligned after internal plaster.
04/06/2020
14/06/2020
10 days
10 days
04/06/2020
14/06/2020
Flooring in shops, offices, foyers and granite cladding.
Fronts available but ON HOLD from client.
After completion of external texture work.
26/06/2020
13/08/2020
48 days
20 days
06/06/2020
48 days
26/06/2020
13/08/2020
Office doors, shop glasss doors, windows & vents.
Work front available BUT agency not yet finalized by client.
Activity aligned after flooring is completed.
09/07/2020
30/07/2020
21 days
30 days
09/06/2020
21 days
09/07/2020
30/07/2020
Facade work
Work front available BUT agency not yet finalized by client.
Activity aligned after external texture.
21/06/2020
04/09/2020
75 days
30 days
22/05/2020
75 days
21/06/2020
04/09/2020
Internal wiring & MCB
on hold from client
Activity aligned after doors are fixed.
30/07/2020
09/08/2020
10 days
7 days
23/07/2020
10 days
30/07/2020
09/08/2020
Putty final coat
Activity aligned after internal electrical work. Putty final coat to be done before possession, each floor will take 3 days
09/08/2020
27/08/2020
18 days
18 days
09/08/2020
27/08/2020
CP, Sanitary & Housekeeping
Activity aligned after completion of final coat of putty.
27/08/2020
11/09/2020
15 days
15 days
27/08/2020
11/09/2020
UGWT
Pardi steel complete
20/05/2020
19/06/2020
30 days
30 days
20/05/2020
19/06/2020
Backside ramp slab
Complete
Structural design as per client (half protion) and RCC portion as per Structural drawings.
20/05/2020
19/06/2020
30 days
30 days
20/05/2020
19/06/2020
Electric cable tray & lighting
ON HOLD from client
Work front available from 01/03/2020.
31/05/2020
25/06/2020
25 days
7 days
24/05/2020
25 days
31/05/2020
25/06/2020
Fire Sprinklers & vertical lines
Agency not finalized yet
Work front available from 01/03/2020.
09/06/2020
04/07/2020
25 days
15 days
25/05/2020
25 days
09/06/2020
04/07/2020
Trench & Sump
ON HOLD from client
Work front available from 01/03/2020.
03/06/2020
08/06/2020
5 days
10 days
24/05/2020
5 days
03/06/2020
08/06/2020
3rd basement plaster.
1 wall remaining overall complete
30/05/2020
09/06/2020
10 days
10 days
30/05/2020
09/06/2020
Floor finish
2nd basement complete, 1 st & 3rd basement remaining
10/06/2020
30/06/2020
20 days
20 days
10/06/2020
30/06/2020
Final coat paint
Not finalized yet
01/07/2020
26/07/2020
25 days
25 days
01/07/2020
26/07/2020
Lift Girder fixing as required.
Agency not finalized yet
No approval yet
20/05/2020
14/06/2020
25 days
5 days
15/05/2020
25 days
20/05/2020
14/06/2020
Lift Order & Delivery
14/06/2020
24/07/2020
40 days
40 days
14/06/2020
24/07/2020
Lift Installation
25/07/2020
08/09/2020
45 days
45 days
25/07/2020
08/09/2020
Common Amenities, Exterior Work & Landscaping, compound wall, granite work, planters, etc.
Front steps, Passage masonary RCC work complete.
30/07/2020
29/08/2020
30 days
30 days
30/07/2020
29/08/2020
Transformer, GEB meter, earthing, etc.
on hold from client.
After completing UGWT & its floor finish with paver work/road work.
04/07/2020
02/09/2020
60 days
30 days
04/06/2020
60 days
04/07/2020
02/09/2020
False ceiling in passages.
Agency not finalized yet
After completion of terrace water proofing.
26/06/2020
21/07/2020
25 days
20 days
06/06/2020
25 days
26/06/2020
21/07/2020
Txture work in passages.
Not finalized yet
After completion of flooring work
30/07/2020
14/08/2020
15 days
15 days
30/07/2020
14/08/2020
External lighting work.
Not finalized yet
No agency to be hired as per client's decision. PMC working for approvals & options with help of vendor.
04/09/2020
19/09/2020
15 days
30 days
05/08/2020
15 days
04/09/2020
19/09/2020
Signboards/ Nameplate
Not finalized yet
Activity aligned after final putty is completed.
27/08/2020
30/08/2020
3 days
30 days
28/07/2020
3 days
27/08/2020
30/08/2020
Stair railing
Agency not finalized yet
Activity aligned with flooring
16/08/2020
05/09/2020
20 days
30 days
17/07/2020
20 days
16/08/2020
05/09/2020
trial
19/04/2020
23/04/2020
4 days
4 days
19/04/2020
23/04/2020
Trial 2
NA
20/04/2020
25/04/2020
5 days
5 days
20/04/2020
25/04/2020
There are no rows in this table