icon picker
PRD: PROJECT NOVA

Amazon Methodology Product

Abstract

Produce a methodology for enhancing the DB2 presentation to provide integrated, comprehensive and simultaneous communication of design aesthetic , performance and metrics.
Project:
Amazon DB2 Presentation Development
EDIT INFO
TL;DR:
Methodology for enhancing DB2 Presentation content
Team:
@NEXT
Status:
@Engineering
Expected Release Date:
Mar 18, 2021

Problem Alignment

Presentation format does not feel integrated, elements of the design feel segregated without the ability to asses simultaneously
Increased interactivity required
Model data is not used to its potential
Presentation requires greater consistency

Solution Alignment

Provide a presentation methodology to provide simultaneous review of design aesthetic, performance and metrics
Provide ability to review live implications on metrics based on design options
Produce enriched data models, leverage this data and present in consistent and easily digestible format
Increase ability to make quick informed decisions
Used by all framework lead designers and usable by their project teams without the need for specialist technology teams
Create a consistent output for all lead designers
Key data to be presented; Cost metrics, Workplace metrics, Sustainability performance, Product information
Solution should improve efficiency and quality without incurring additional time

Deliverables

N.B. Guidance documentation noted below will be compiled into a single document

1. Product BIM Library [SM]

Methodology and tools required to enable BOQ information to be generated from the BIM model.
Produce initial Revit object library based on Project Eames content (where content is available from manufacturers)
Content to be hosted on agreed CDE platform
Determine model requirements to produce
Guidance document to explain methodology

2. Design Aesthetic Visualisation [SM]

Methodology and tools required to enable design aesthetic to be presented in format to meet identified solution alignment above
Guide document to explain methodology

3. Cost Plan [BOQ] Visualisation [SM]

Methodology and tools/ platform required to provide BOQ information
Determine methodology/ platform for BOQ generation
Guide document to explain methodology

4. DB2 Presentation Methodology [SM]

Methodology for utilising these deliverables and integrating into presentation
Guide document to explain methodology
Identify changes

5. DB2 Presentation Restructure Proposal [JC]

Revised deck structure guide
Example document using test/ pilot project

Open Issues & Key Decisions
Resolved
Date Raised
Issue or Thought
Answer
Who Raised It
1
2/4/2021
Can BOX be used to host Product BIM Library? If so how to obtain access and folder setup
Plan A Amazon to setup BIM 360, Plan B/ interim, potentially on BOX, workplace guidelines
SM
Stephen Magee
2
2/4/2021
Do Amazon have Revit & Enscape software/ licences? or the desire to do so to re-create experience exactly?
Contract with Autodesk for ops
SM
Stephen Magee
3
2/4/2021
Are there any Amazon BIM naming standards?
Not yet
SM
Stephen Magee
4
2/4/2021
Do all Lead designers use Enscape?
TBC, happy to dictate for right solution
SM
Stephen Magee
5
2/4/2021
What is the driver for mandating Uniclass 2015?
Setup call with Karl and Anand (cost)
SM
Stephen Magee
6
2/4/2021
Would Amazon want access to BIM 360 web?
Yes, see above plan for BIM 360
SM
Stephen Magee
7
2/15/2021
Where should deliverables documentation be saved?
SM
Stephen Magee
There are no rows in this table

Product - Enscape

VR Presentation Software

Utilise BIM panel and map features
Working with Encsape to improve visibility of required parameters
Currently too many showing in BIM panel to easily identify required information
Enscape BIM.png

Product - Assemble Systems

Cost Management/ BOQ Software

Web based platform to provide model data analysis
Ability to view powerful scheduling alongside model views
Assemble1.JPG
Includes model review tools
Assemble2.JPG
Potential for integration with Power BI for dashboard presentations
Assemble3.JPG

Timeline

Key Milestones

Date
Milestone
Description
1
Wed, Feb 24
Assemble Test WIP
Present progress on Assemble [BOQ] platform testing
2
Wed, Mar 3
Test Project Development WIP Presentation
Use previous project as test for deliverables [50-75% complete]
3
Wed, Mar 17
Final Presentation
Present completed project deliverables
4
Wed, Mar 24
Pilot Presentation [TBC]
Present Pilot project [Potentially VIEXX]- Date TBC, need to review selected project programme
5
Wed, Apr 7
Adapt & Update
Incorporate changes and lessons learnt from pilot project and final presentation comments
6
Wed, Apr 7
Amazon & Framework Release
Issue deliverables documentation to wider Amazon team and other Lead Designers [to be discussed]