As discussed (1st actions hilighted in bold):
Tunnel Matrix with PIC – VER team (Civil + Electrical profiles) TSC – 2 units (MTE and QYP) (with Hira) (Civil + Electrical profiles) Britomart TRP (OHLE) room – Hira (Electrical profile) Britomart SIG,LV & Coms rooms – Sahand (Electrical profile)
Containment started ALB done, in progress in ATK Cables - to start 8/05 ALB BRI SIG room – to start 8/05
Progress program with Liam (PY?)
Schedule Go/Nogos (ahead of construction start) To come with Akhila/Sahand and Hira – 2 weeks’ time (19/05) – SPW team
i. Nick - Superintendent
ii. Sahand - Project Eng
iii. Hira - Project Eng.
with stations teams (80% clear) i. SPW Linear work until the room with terminations
ii. Containment by Station team from tunnel to the room
iii. Inside the room, only SPW Linear scope (including containment)
SPW linear will be part of the Power On AOT North – 19/03/2024 TBC BR,
Maxime