Use this table as your master table to plan work. If you want to change the start date see the page.
To wipe this table click this button
Delete rows
Project planning table
Project Phase
Action
Teams Required
Type
Duration Working Days
Start Date
End Date
Project team
Team cost per week
Other costs and payments
Income
Work on Project 1
1
25 days
2020-09-07
2020-10-09
£400.00
Insurance
-
1 day
2020-09-07
2020-09-07
£0.00
£1,000.00
Start up funds
0
1 day
2020-09-07
2020-09-07
£0.00
£25,000.00
Work on Project 2
1
15 days
2020-10-05
2020-10-23
£450.00
Work on Project 3
2
63 days
2020-10-12
2021-01-06
£880.00
Sales period to sell Project 1
0
15 days
2020-10-12
2020-10-30
£0.00
London investment grant
0
1 day
2020-10-19
2020-10-19
£0.00
£10,000.00
Sell Project 1
0
1 day
2020-11-04
2020-11-04
£0.00
£5,000.00
Work on Project 4
1
39 days
2020-11-09
2020-12-31
£450.00
Start up loan
0
1 day
2020-12-16
2020-12-16
£0.00
£50,000.00
Loan repayment
0
1 day
2020-12-21
2020-12-21
£0.00
£10,000.00
There are no rows in this table