Skip to content
Farro Project Estimation
Share
Explore

icon picker
Project Summary

333.png
Data Integrations
1
Source Data
Target Data
Integration / Operators
1
BambooHR
BioTime
New and Updated Employee Records pushing to BioTime
2
BioTime
BambooHR
Hours worked / Leave Used each day being synced to bambooHR
3
BambooHR
Ipayroll
Hours Worked / Leave used pushed into Ipayroll
4
Ipayroll
BambooHR
New Leave Balances Pushed into BambooHR after payroll processed
5
Ipayroll
BambooHR
Payroll Slip information pushed into bambooHR
There are no rows in this table


Proposal Quote / Estimation
0
Name
Estimated Hours
Aprox Cost
View
1
Prep
23
$2,300.00
View Tasks
2
Configuration
85
$8,500.00
View Tasks
3
Testing/Review
10
$1,000.00
View Tasks
4
Modifications Implemented
15
$1,500.00
View Tasks
There are no rows in this table
$13,300.00
excluding GST



Want to print your doc?
This is not the way.
Try clicking the ⋯ next to your doc name or using a keyboard shortcut (
CtrlP
) instead.