County name
6
Solano County
Contra Costa County
San Mateo County
Napa County
Alameda County
Marin County
Solano County
7
Fairfield
5th Cycle’s progress: 49%
Vacaville
5th Cycle’s progress: 99%
Vallejo
5th Cycle’s progress: 10%
Benicia
5th Cycle’s progress: 4%
City Council: SYoung@ci.benicia.ca.us, TCampbell@ci.benicia.ca.us, CStrawbridge@ci.benicia.ca.us, LLargaespada@ci.benicia.ca.us,
Rio Vista
5th Cycle’s progress: 125%
Suisun City
5th Cycle’s progress: 10%
Dixon
5th Cycle’s progress: 119%
Contra Costa County
20
Antioch
05/31/22
Monument Impact, Debra Ballinger debra@monumentimpact.org
5th Cycle’s progress: 38.1%
Alexis Morris, Planning Manager planning@ci.antioch.ca.us
04/2021
Entered into a contract with a consultant to prepare the new Housing Element. They expect to concurrently update the Safety Element and draft a new Environmental Justice Element. This additional effort will be going to the City Council for approval on July 27. They have not developed a public schedule just yet, but we hope to have all efforts completed well ahead of the 2023 deadline. There will be ample opportunities for public participation as we move further into the process.
7/15/21
reached out via email → response: no progress made
11/9/21
updated their docs and schedule on website
1/13/22 updated coda with previous meetings and current winter 2022 timeline/planned schedule
1/26/22 and asked to present to staff on playbook and learn more about update
they said they will watch the Pinole presentation and decide
3/8/2022 attended city council meeting to support transitional housing overlay
Passed 3-2
05/31/22 Update
Public comment period: May 16, 2022-June 15, 2022 - written comments may be submitted to Anne Hersch, Planning Manager, at
sent comment letter > overall good
09/12/22
No updates


San Pablo
5th Cycle's progress: 8%
Tyler Libby, Planning Manager (510) 215-3036
emailed 8/9
sent out comm survey Jan 2022
Hercules
November 2021 - Stakeholder interviews and outreach
5th Cycle's progress: 68%
Robert Reber, Interim Community Development Director (510) 799-8248
been added to list of interested parties → will be contacted with further information
reached out 11/30/21
stakeholder interview with Karen 12/22/21
1/18 no new info on website
3/3 update
(now accepting responses)
(workshop #1 scheduled for March 21 at 7:00 PM)
Stakeholder Interviews and Focus Groups
09/12/22
DRAFT RELEASED!
Comments may be emailed to Tim Rood, Community Development Director,


El Cerrito
Updated 7/24/22
5th Cycle's progress: 87%
Sean Moss, Planning Manager (510) 215-4359
reached out 7/26 via email
no updates yet
told to check back in Fall/Winter
reached out 11/9 via email
11/30 no response...
Fred from SRVCC recommended reaching out to Lisa Montoyama, a city council member with lots of housing experience
1/13 reached out to Ashoori Aissia, Housing Analyst
no updates on website
09/12/22
PUBLIC REVIEW DRAFT: 2023-31 HOUSING ELEMENT UPDATE NOW AVAILABLE
- PUBLISHED JULY 19, 2022
We are please to share the draft 2023-31 Housing Element Update. The community is welcome to provide comments to City staff through August 29, 2022. Written comments can be submitted to and verbal comments can be shared at the on Tuesday, August 16, 2022 or by contacting 510-215-4361.
Brentwood
5th Cycle's progress: 213%
Erik Nolthenius, Planning Manager (925) 250-6583
reached out 11/9
should be kicking the project off in the next week or two
recently approved a contract with Kimley-Horn to provide assistance with the Housing Element
11/19 - will be kicking off project soon :)
1/13 sent an email for an update about HE and plugged Playbook
no info on website about the HE update
Erik responded 1/14
Website should be live in February
Looking at a joint meeting with the Planning Commission and City Council at the end of March
Not updating any other elements concurrently
Housing Element Update Work Program pdf in email
January 2022 update
In a contract with Kimley-Horn as the consultant
Website should be live in February
Looking at a joint meeting with the Planning Commission and City Council at the end of March
Not updating any other elements concurrently
3/17/22 requested update form Erik and plugged the Playbook
7/26/22
No updates
09/12/22
Comments and feedback on the Draft Document will be collected from August 25, 2022, to September 27, 2022.


Pleasant Hill
4CL
5th Cycle's progress: 15%
Troy Fujimoto, Tfujimoto@pleasanthillca.org
City took public comments on potential sites through Aug 11, 2021
9/22 update
Currently in “Phase 5: Preparing the Plan”
No scheduled upcoming meetings
reached out 1/18
Pinole
5th Cycle's progress: 3%
(510) 724-8912
reached out 1/18
Danville
Launch: Winter 2021
Genesis of the Tri-Valley, Monith Ilavarasan milavarasan1@gmail.com
5th Cycle's progress: 51% 6th Cycle: 2241 units
David Crompton, Chief of Planning (925) 314-3349
10/1 update
Took poll on TownTalks webpage and 2/3 of people think housing is not affordable in Danville
July 9, 2021 filed RHNA appeal
1/13 no new updates on website
Sent Housing Policy Recommendations letter 3/9
07/24/22
The is now available for a public review period that will conclude on August 1, 2022.
09/12/22
Currently in 90 day initial state review period

Clayton
June 2021 - Project Kick-off and City Tour
5th Cycle’s progress: 4.4%
Dana Ayers, Community Development Director (925) 673-7300
reached out 7/26 via email
Council authorized execution of the professional services agreement. The estimated timeline for completion of the update is on pdf page 110 of the agenda packet.
The May 18, 2021, agenda full packet can be downloaded here:
reached out 11/30
took HE survey 12/1
34% of respondents don’t support any new housing in Clayton
1/13/22 no new updates on website
7/24/22
Finished 30-day public review and held 4 community comment meetings
Submitted draft to HCD on July 14, 2022
09/12/22
The Draft EIR comment period will begin on August 19, 2022, and close on October 3, 2022.

Pittsburg
Pittsburg Youth Action, Manisha Rattu rattumanisha@gmail.com
5th Cycle's progress: 43%
Jordan Davis, Director of Community and Economic Development/Acting Planning Manager (925) 252-4015
Notes on Community Engagement
3 Visioning Workshops in 2019
Online Workshops Series in 2020
2 Land Use Alternatives Workshops
Land Use Stakeholders Meeting
3/3/2022 Update
Emailed Jordan Davis about HE update and playbook

Unincorporated, Contra Costa County
CCC Draft Housing Element available for public review March - April 2022
4CL
5th Cycle's progress: 80%
Will Nelson
Reached out to Amalia 1/18
3/9 Planning Commission Meeting and Study Session for Stronger Communities Element
Provided

Martinez
5th Cycle's progress: 7%
no reply during first round of emails - reached out again 7/26
Reached out via email 10/25 for update
Special Advisor Patrick O’Keefe from Management Partners will present the above remaining elements of the Revised Draft General Plan to the City Council and Planning Commission during the third joint meeting on January 12th. Staff will continue taking notes of the comments made by the City Council, Planning Commission, and public and summarize these in a document that will be posted on the City’s General Plan Update webpage. The document will be updated to reflect comments made at each joint meeting and it will also be updated on a monthly basis to include additional comments received after the joint meetings. Public comments on the Revised Draft General Plan can be emailed to GPcomments@cityofmartinez.org.
reached out for update 1/18
7/26/22
No updates - could only find info on GP update
9/12/22

Oakley
5th Cycle's progress: 66%
Joshua McMurray
held a meeting 9/1 with planning team, DeNovo and community members
7/24/22 update
- Submit comments by: August 5, 2022
By Mail: City of Oakley, Planning Division, 3231 Main Street, Oakley, CA 94561
By Email:

Richmond
Richmond Land, Dulce Galicia dulce@richmondland.org
5th Cycle's progress: 24%
(510) 620-6706
emailed 8/9
reached out 1/13
Planning on getting started at end of month
want admin draft by July and public review draft by august
website and timeline will be updated in February
Dulce from Richmond Land has connections with city council members: Melvin, Eduardo, Claudia

Lafayette
Inclusive Lafayette, Jeremy Levine
5th Cycle's progress: 80%
Greg Wolff, Planning and Building Director (925) 299-3204
Concord
June 2021 - Data collection begin
EBHO, Sophia DeWitt sophia@ebho.org
5th Cycle's progress: 4%
Mindy Gentry, Planning Manager (925) 671-3369
Took Concord Survey 1/3
1/13 no new updates on website
Sent Policy Recommendations Letter 3/28
7/24/22
The public review period ended June 27, 2022. We are currently reviewing comments and taking into consideration your input as we prepare the next Draft Plan, which will is projected to be posted for review in July 2022.
09/12/22
the Draft 6th Cycle Housing Element for the City of Concord was made available for a 30-day public review period from May 27, 2022, through June 27, 2022.
This draft will be sent to the California Department of Housing and Community Development (HCD) for a 90-day review period on Monday, August 15th, 2022.

Orinda
Feb 2022: EIR scoping period, community workshop
5th Cycle's progress: 81%
orindaplanning@cityoforinda.org (925)253-4210
1/13 concurrently updating, HE, downtown precise plan, and safety element
can create own HE on website
signed up for notifications
Attended 1/20 Orinda Downtown Planning and HE Subcommittee Meeting
7/26/22
Public comment period ended

Moraga
Summer 2021: Select consultant, launch project
Inclusive Lafayette, Jeremy Levine
5th Cycle's progress: 31%
Afshan Hamid, Planning Director ahamid@moraga.ca.us
emailed 8/2 for update on schedule and plan for proper outreach and community engagement
1/25 updated timeline
upcoming meetings + events per website
Tuesday, January 25, 2022 at 6:30pm Bollinger Valley Neighborhood Meeting
Wednesday, February 9, 2022 at 6:30pm Bollinger Valley Town Council Meeting.
Wednesday, February 23, 2022 at 6:30pm Housing Site Selection Town Council Meeting
Environmental Review Scoping Meeting (TBD)
Housing Survey (TBD)
Timeline on page 56
7/24/22 Update
You can review the HCD Working Draft Housing Element at . Submit comments to makemoragahome@moraga.ca.us by July 30, 2022.

San Ramon
4CL
5th Cycle's progress: 97%
Lauren Barr, Planning Services Manager (925) 973-2567
Working on General Plan, HE Update, and CAP
9/22
Survey for feedback that will help guide the General Plan, Housing Update, and Climate Action Plan Update process - open until October 31st, 2021 (https://www.surveymonkey.com/r/PPNF6SY)
Currently in Phase 1
No upcoming meetings
Held GP, HE, AND CAP meeting on 10/19
1/13 no new info on website
added previous meetings to coda
still in phase 1
phase 4 is HE
BECAUSE THEY ARE UPDATING THEIR CAP, GP, AND HE THIS WOULD BE AN INTERESTING AREA TO ENGAGE IN AND MAKE SURE THE POLICIES ARE ALL CONSISTENT ... I ALSO FEEL LIKE WE COULD HAVE A GOOD IMPACT HERE CONSIDERING THE RHNA NUMBERS, AND OUR EXISTING PARTNERS
1/2/22 currently in HE update phase
2/3/2022 update
Website states that they are currently in Phase 4: HE update
7/24/22
The Draft 2023-2031 Housing Element is available for a 30-day public review period, from Friday, May 13, 2022 to Sunday, June 12, 2022. The Draft 2023-2031 Housing Element is available below and on the website:

Walnut Creek
Diablo Valley For Everyone, Aaron Eckhouse aaron@cayimby.org
5th Cycle's progress: 47%
Ethan Bindernagel, Planning Manager (925) 256-3530
reached out 1/18
Tiny homes project in the city → DV4E is engaged in this development
update on progress to planning commission on Feb 10 and city council on Feb 15
Walnut Creek Housing and Community Development Council Special Meeting 1/31/2022
Introduction to the Housing and Safety Elements update, and review of the draft Community Engagement Plan
3/14/22 update
sent email to Andrew Smith about Playbook and timeline
7/24
Released HE Update draft for 30-day public review period through August 19, 2022
1/27/22 update
Santa Clara County
18
Santa Clara County
August 2021: Contracts awarded
5th Cycle’s progress: 666%
Rob Eastwood,
Campbell
Housing Element 2015-2022 p327
5th Cycle’s progress: 29%
Daniel Fama, Senior Planner (408) 866-2193
Cupertino
5th Cycle’s progress: 18%
https://www.cupertino.org/Home/Components/StaffDirectory/StaffDirectory/41/1707?sortn=STitle&sortd=asc&npage=2
Gilroy
5th Cycle’s progress: 98%
Manny Bhandal, Planning Commissioner (408) 846-0451
Los Altos
5th Cycle’s progress: 74%
Jon Biggs, Planning Commission Liaison (650) 947-2635
Los Altos Hills
5th Cycle’s progress: 31%
Zachary Dahl, Planning and Building Director (650) 947-2507
Los Gatos
5th Cycle’s progress: 14%
Sally Zarnowitz, Planning Manager (408) 354-6873
New website in progress
Milpitas
5th Cycle’s progress: 61%
Ned Thomas, Planning Director
Monte Sereno
5th Cycle’s progress: 77%
Jeannie Hamilton, City Planner
Morgan Hill
5th Cycle’s progress: 139%
Mountain View
Intro Goals and Data Gathering Spring 2021
5th Cycle’s progress: 77%
Palo Alto
May 2022: Draft Housing Element Update May 2022: Draft Supplemental EIR May 2022-July 2022: HCD Review & Certification July 2022-Oct 2022: Community Engagement Sept 2022: Final Housing Element & Supplemental EIR Documents Nov 2022: CC Adoption
Palo Alto Forward, SV@Home
5th Cycle’s progress: 17%
Jonathan Lait, Director (650) 329-2679

Housing Element Working Group Meeting #11

Thursday, January 13, 2022
5:30 PM – 8:30 PM
Click to join Zoom.

Housing Element Working Group Meeting #12

Thursday, February 3, 2022
5:30 PM – 8:30 PM
Click to join Zoom.
San Jose
Fall 2021: Public Outreach begins Fall 2022: PlanCom and CC public hearings on Revised Draft Housing Element Jan 31, 2023: Adopted Housing Element due to HCD
Sacred Heart Community Service, Matt Kingmattk@sacredheartcs.org
5th Cycle’s progress: 30%
Santa Clara
Fall 2021/Winter 2022: Draft Element Prep & Stakeholder Outreach Winter/Spring 2022: Community Meeting and Public Review of Draft Housing Element Summer 2022: PlanCom Hearing Fall 2022: City Council adoption Winter 2022: HCD Review & City Revisions
Santa Clara Community Advocates SV@Home Silicon Valley Leadership Group Law Foundation Catalyze SV
5th Cycle’s progress: 64%
Saratoga
5th Cycle’s progress: 12%
Stanford (unincorporated)
Sunnyvale
Dec 2021: Housing & Human Services/PlanCom Joint StudySession Jan 2022: CC Study Session Feb 2022: Stakeholder interviews, Community Workshops, Online Survey March 2022: Public Review Draft Housing Element April 2022: Joint HHS/PlanCom Study Session, Community Workshop May 2022: CC Study Session, May 2022-Sept 2022: Revised Housing Element for HCD Review Oct 2022: CEQA Document Nov 2022: HHS Hearing Dec 2022: PlanCom Hearing, City Council Hearing, Final Housing Element
5th Cycle’s progress: 29%
Kent Steffens, City Manager (408) 730-7480
San Mateo County
20
Atherton
5th Cycle’s progress: 88%
Belmont
5th Cycle’s progress: 23%
Brisbane
5th Cycle’s progress: 56%
Burlingame
5th Cycle’s progress: 34%
Colma
5th Cycle’s progress: 79%
Daly City
5th Cycle’s progress: 39%
East Palo Alto
Housing Element 2015-2023
5th Cycle’s progress: 13%
Foster City
5th Cycle’s progress: 117%
Half Moon Bay
5th Cycle’s progress: 34%
Hillsborough
5th Cycle’s progress: 57%
Menlo Park
5th Cycle’s progress: 111%
Millbrae
https://www.ci.millbrae.ca.us/home/showdocument?id=6623Housing Element 2015-2023
5th Cycle’s progress: 2%
Pacifica
https://www.cityofpacifica.org/civicax/filebank/blobdload.aspx?BlobID=6667Housing Element 2015-2023
5th Cycle’s progress: 11%
Portola Valley
Housing Element 2015-2023
5th Cycle’s progress: 42%
Redwood City
https://www.redwoodcity.org/home/showdocument?id=5127Adopted 2014: HE 2015-2023
5th Cycle’s progress: 46%
San Bruno
5th Cycle’s progress: 9%
San Carlos
5th Cycle’s progress: 54%
San Mateo
https://www.cityofsanmateo.org/1675/2015-2023-Housing-ElementHousing Element 2015-2023
5th Cycle’s progress: 35%
South San Francisco
https://www.ssf.net/home/showpublisheddocument?id=476Housing Element 2015-2023
5th Cycle’s progress: 33%
Woodside
Housing Element 2015-2023
5th Cycle’s progress: 82%
Napa County
5
American Canyon
Housing Element 2015-2023
Calistoga
https://www.ci.calistoga.ca.us/home/showpublisheddocument?id=12096Housing Element 2015-2023
Napa
St. Helena
Yountville
Sonoma County
10
Cloverdale
Kick-off workshop by 4Leaf Dec 2021
5th Cycle’s progress: 34%
Rafael Miranda, rmiranda@ci.cloverdale.ca.us, 707-894-1726
Cotati
no draft yet
5th Cycle’s progress: 36%
Jon-Paul Harries JPharries@cotaticity.org, (707) 665-3636
Healdsburg
Survey March 2022 no draft yet
5th Cycle’s progress: 111%
David Woltering, Interim Community Development Director, Planning@ci.healdsburg.ca.us
Petaluma
https://cityofpetaluma.org/documents/the-housing-element-2015-2023/Housing Element 2015-2023
no draft yet
5th Cycle’s progress: 77%
Rohnert Park
http://rpcity.granicus.com/MetaViewer.php?view_id=3&clip_id=484&meta_id=41821Housing Element 2015-2023
Adopted agreement with consultants (4Leaf in November 2021)
5th Cycle’s progress: 104%
Santa Rosa
Housing Element 2015-2023 is within Chapter 4 of the General Plan
Release public review draft 30 days - April
5th Cycle’s progress: 24%
Sebastopol
draft released July, comments due August 18th
5th Cycle’s progress: 31%
Sonoma
October 2021 - February 2022, Evaluate/Review Existing Conditions, Plans, and Programs
5th Cycle’s progress: 48%
Windsor
April 2022: Planning Commission meeting on HE draft no draft yet
5th Cycle’s progress: 25%
County of Sonoma
Planning Commission hearing in Oct 2022
5th Cycle: 515
Alameda County
15
Alameda
RFP for EJ Element expected to be chosen by June or July
5th Cycle’s progress: 47%
(510) 670-5400
Albany
5th Cycle’s progress: 44%
(510) 528-5760
Berkeley
5th Cycle’s progress: 38%
Alex Amoroso and Leslie Mendez, Project Managers
Dublin
The City of Dublin is currently working on our Housing Element Update, where we have held two public meetings to date. The next public meeting will tentatively be held on May 18th. We anticipate adoption of our Housing Element in Summer 2022. In addition to the Housing Element, the City plans to update our Land Use Element for consistency with the Housing Element. The City also anticipates updating our Safety Element and adding environmental justice policies. For additional information, please visit:
5th Cycle’s progress: 102%
Michael Cass, Principal Planner (925) 833-6628
has been ammended very much
East County Area
Emeryville
5th Cycle’s progress: 24%
Miroo Desai, Senior Planner (510) 596-3785
Fremont
5th Cycle’s progress: 69%
7/26/22
The 30-day public comment period will be open from Friday, July 8 through Monday, August 8. Members of the public are encouraged to review the documents below and email any comments to
Hayward
We received a LEAP grant from the State to update our Housing Element and we are currently drafting the RFP for consultant support on the project. We plan to send the RFP out in the next month and to kick off the project this summer. The full scope of work for the project is unknown at this time because we will work with a consultant to develop a scope, but we do anticipate that our RFP will identify the following General Plan Updates, in addition to the Housing Element Update:
5th Cycle’s progress: 32%
Christina Morales, Housing Division Manager (510) 583-4311 Leigha Schmidt Leigha.Schmidt@hayward-ca.gov
Livermore
5th Cycle’s progress: 46%
Tricia Pontau, Assistant Planner (925) 960-4450.
Newark
5th Cycle’s progress: 48%
Art Interiano, Deputy Community Development Director (510) 578-4330
Jan 2022: Will be updating their Health and Safety and Environmental Hazards soon
Oakland
Causa Justa: Just Cause
5th Cycle’s progress: 60%
Diana Perez Domencich, Planner II 510-238-3550
Piedmont
The full scope of work for the project is unknown at this time because we will work with a consultant to develop a scope, but we do anticipate that our RFP will identify the following General Plan Updates, in addition to the Housing Element Update.
5th Cycle’s progress: 39%
Pierce Macdonald-Powell,
reached out via email 7/26 for update
Responded with website
seems like there are no concrete plans for outreach or upcoming meetings
Pleasanton HE Draft Sites Inventory Feedback Letter.pdf
Pleasanton
Introductory Kick-Off Meetings: April - May 2021 Housing Needs Assessment; Policies and Programs Review: May - September 2021 Initial Sites Inventory, Methodology and Criteria: July - September 2021 Preparation of Comprehensive CEQA Project Description: November 2021 Environmental Review Scoping and NOP: December 2021 CEQA Sites Inventory Selection Meetings: December 2021 – January 2022 Prepare Technical Studies; Draft Housing Element and EIR: December 2021 – May 2022 HCD 60-Day Review Period & Meetings to Review PRD HE: June - July 2022 Public Draft Program EIR (45-Day Review Period): July-August 2022 Final Sites Inventory and Final Housing Element: August - Oct 2022 Public Hearings to adopt Housing Element and Final EIR: Nov 2022 - Jan 2023
East Bay 4 Everyone, Genesis
5th Cycle’s progress: 59%
Shweta Bonn, Senior Planner (925) 931-5611
Pleasanton HE Draft Sites Inventory Feedback Letter.pdf
San Leandro
5th Cycle’s progress: 7%
Andrew Mogensen, Planning Manager
took HE survey on 12/9

Union City
5th Cycle’s progress: 29%
Marin County
12
Belvedere
5th Cycle’s progress: 16%
Corte Madera
5th Cycle’s progress: 188%
Fairfax
5th Cycle’s progress: 89%
Larkspur
5th Cycle’s progress: 55%
Mill Valley
5th Cycle’s progress: 47%
Novato
5th Cycle’s progress: 40%
Ross
5th Cycle’s progress: 38%
San Anselmo
5th Cycle’s progress: 58%
San Rafael
Marin Environmental Housing org
5th Cycle’s progress: 18%
Jacob Noonan, Housing Program Manager:
Sausalito
5th Cycle’s progress: 36%
Tiburon
5th Cycle’s progress: 13%
Marin County
Jan 20th workshop to use balancing act tool. Interactive workshop to teach people how to use balancing act tool
5th Cycle’s progress: 86%
Met with Jillian Zieger who is in charge of the HE and she wants more youth to attend the community listening meetings
San Francisco County
1
San Francisco
1
Want to print your doc?
This is not the way.
Try clicking the ⋯ next to your doc name or using a keyboard shortcut (
CtrlP
) instead.