Shelter renovation - Project Charter
Oleksandra Ta Chan
Anna Lykhohliad
Daniil Podshybiakin
Project sponsor - John Johnenko
PM - Taras Tarasenko
Project Purpose
The purpose of this project is to construct a secure underground shelter of 150 square meters equipped with essential utilities, including ventilation, electricity, and a sanitation system. The shelter is intended to provide safe refuge during emergencies, ensuring the well-being of individuals within the designated area. Given current geopolitical and environmental concerns, this project aims to enhance preparedness and resilience. Must be accessible to people with limited mobility
Project Objectives
Assessment of sanitary conditions Evaluation of the feasibility of restoration Collection and preparation of requirements for the contractor Opening of the tender for contractors Selection and approval of the contractor Сontracting with the contractor, obtaining specifications for the construction Project Description
As part of a charity campaign, our commercial organisation wants to renovate a shelter for an elementary school in the Sumy region in a rural area. We want children in the village to be safe during air alerts. Today, the school's shelter is an old Soviet shelter, which is unsuitable for use due to the impact of natural factors, aging, and looting. To implement the project, our organisation decided to choose a local contractor, which would also support local businesses in the region.
Value proposition - safety for children
Profit proposition - no profit. We get reputational benefits from financing the project.
Human value proposition - our employees are aware of the company's charitable activities.
Project Scope
Conduct a community survey on shelter needs Defining requirements for a construction company Preparing a schedule plan Selection and contract agreement with a construction firm Monitoring project progress according to the schedule
Project Stakeholders
Client Representative/Sponsor: Name, Surname, Contacts Client Project Manager: Name, Surname, Contacts Construction Firm: Name, Surname, Contacts Safety and Compliance Inspectors: Name, Surname, Contacts Local Authorities: Name, Surname, Contacts
Project Schedule
Project Budget
Estimated total cost: $165,000 - $250,000 (depending on materials and labor costs) Construction materials: $80,000 - $120,000 Utilities and systems: $30,000 - $50,000 Contingency fund: $5,000 - $20,000
Project Risks
Project success criteria
To implement the project timely and efficiently
The project should be able to provide 50 pupils with decent conditions for learning
The project costs did not exceed $250,000.
The community has a safe shelter that will serve as an educational space for children and the community in the future.