Shelter renovation - Project Charter

sheet-of-paper

Oleksandra Ta Chan Anna Lykhohliad Daniil Podshybiakin

Project sponsor - John Johnenko
PM - Taras Tarasenko

Project Purpose

The purpose of this project is to construct a secure underground shelter of 150 square meters equipped with essential utilities, including ventilation, electricity, and a sanitation system. The shelter is intended to provide safe refuge during emergencies, ensuring the well-being of individuals within the designated area. Given current geopolitical and environmental concerns, this project aims to enhance preparedness and resilience. Must be accessible to people with limited mobility

Project Objectives

Assessment of damage
Assessment of sanitary conditions
Evaluation of the feasibility of restoration
Collection and preparation of requirements for the contractor
Opening of the tender for contractors
Selection and approval of the contractor
Сontracting with the contractor, obtaining specifications for the construction

Project Description

As part of a charity campaign, our commercial organisation wants to renovate a shelter for an elementary school in the Sumy region in a rural area. We want children in the village to be safe during air alerts. Today, the school's shelter is an old Soviet shelter, which is unsuitable for use due to the impact of natural factors, aging, and looting. To implement the project, our organisation decided to choose a local contractor, which would also support local businesses in the region.
Value proposition - safety for children ​Profit proposition - no profit. We get reputational benefits from financing the project. ​Human value proposition - our employees are aware of the company's charitable activities.

Project Scope

Conduct a community survey on shelter needs
Defining requirements for a construction company
Conducting a tender
Obtaining the projects
Preparing a schedule plan
Selection and contract agreement with a construction firm
Monitoring project progress according to the schedule
Acceptance of work
Putting into operation

Project Stakeholders

Client Representative/Sponsor: Name, Surname, Contacts
Client Project Manager: Name, Surname, Contacts
Construction Firm: Name, Surname, Contacts
Safety and Compliance Inspectors: Name, Surname, Contacts
Local Authorities: Name, Surname, Contacts
Community

Project Schedule

Table 2
Title
Duration
Description
Assesment and analysis
30 days
Selection and approval of the contractor
30 days
Receiving a project plan from the contractor
20 days
First phase of the implementation
120 days
Second phase of the implementation
120 days
Third phase of the implementation
120 days
There are no rows in this table


Project Budget

Estimated total cost: $165,000 - $250,000 (depending on materials and labor costs)
Major cost components:
Construction materials: $80,000 - $120,000
Labor: $50,000 - $80,000
Utilities and systems: $30,000 - $50,000
Contingency fund: $5,000 - $20,000

Project Risks

Table
Risk
Trigger moment
Mitigation strategies
Limited number of relevant contractors
After 15 days of searching
Conduct additional research on the market of performers in neighboring regions Consider reducing the requirements for contractors
The contractor does not have the appropriate resources to implement the project
At the time of contract negotiations
Termination of negotiations to find a new contractor
The contractor fails to meet the scheduled deadlines
During weekly progress reports During the on-site inspection
Negotiations and search for options to speed up work without compromising quality
The contractor does not report on progress
Reporting delayed by 3 days
Get direct contact with the project manager of the contractor's organization Escalation of the situation to direct management, search for other channels of communication with the contractor
The contractor cannot perform the work within the allocated budget
Upon notification from the contractor during reports, or ad hoc reports or meetings
Military incursion into the community
ruzzia🤡
Donate to Ukrainian defense forces
There are no rows in this table

Project success criteria

To implement the project timely and efficiently
The project should be able to provide 50 pupils with decent conditions for learning
The project costs did not exceed $250,000.
The community has a safe shelter that will serve as an educational space for children and the community in the future.