Procurement

fuse_square
Project |

SOV
Material / Information
Schedule
Required on Job By
Stage
Lead Time (Weeks)
Fully Executed Work Authorization
Air Handling Unit
Jun 18, 2025
12
Mar 26, 2025
LED Lighting Fixtures
Aug 15, 2025
8
Jun 20, 2025
Sanitary Waste Piping
Aug 2, 2025
6
Jun 21, 2025
Footing Rebar
Jul 6, 2025
4
Jun 8, 2025
CMU Blocks
Sep 5, 2025
10
Jun 27, 2025
Structural Steel Beams
Aug 4, 2025
14
Apr 28, 2025
Excavator Rental
Sep 10, 2025
2
Aug 27, 2025
CAT6 Data Cable
Jun 22, 2025
3
Jun 1, 2025
Sprinkler Pipe
Sep 11, 2025
8
Jul 17, 2025
Porcelain Tile
Aug 29, 2025
6
Jul 18, 2025
Escalator Modules
Aug 16, 2025
16
Apr 26, 2025
Toilet Partitions
Aug 25, 2025
5
Jul 21, 2025
Laboratory Fume Hood
Jul 27, 2025
9
May 25, 2025
Office Workstations
Jul 9, 2025
7
May 21, 2025
Waterproofing Membrane
Jun 15, 2025
4
May 18, 2025