~2 PM – Kick off Backup of system (expected 8 hours, Ted to lead)
~4 PM – Diane to resync EDA and DOMO
~430PM – Kim to pull final aging out of DOMO and store for reference when system is restored
~10 PM – Backup finishes and EIT coordinates their final activities
~11 PM – Imagine given go ahead to complete their prepurge steps
~Midnight – Start Purge Process
~9 AM (Or whenever the purge is completed) – Imagine given go ahead to complete their post purge steps (expected 1 hour)
~10 AM – Jenn/Stephen to validate system core function and complete post purge steps
~11 AM – Ted to complete post purge steps with EIT
~Noon – Diane to resync EDA and DOMO
~1230PM – Kim to pull aging report and compare total numbers
~1 PM – Hand system over to traffic for test scripts
~5 PM – Confirm system back and fully functioning