41
Route Selection
10/15/2024
10/25/2024
000
100
Open
Digital Terain Modeling
10/25/2024
11/18/2024
000
100
Open
Plan and Profile Design (PLSCad)
11/22/2024
12/2/2024
000
100
Open
Tower Design
10/15/2024
11/29/2024
000
99
Open
Soil Investigation
11/1/2024
12/21/2024
000
Open
Foundation Design
11/1/2024
11/20/2024
000
Open
Procurement Plan
12/3/2024
4/2/2025
000
Open
Land Acquisition
11/1/2024
12/29/2024
000
Open
UXO
12/5/2024
1/4/2025
000
Open
Access Road
12/1/2024
3/1/2025
000
Open
Foundation
12/1/2024
3/1/2025
000
Open
Tower Erection
1/31/2025
5/1/2025
000
Open
Stringing Works
4/1/2025
6/30/2025
000
Open
Testing & Commissioning
6/30/2025
7/21/2025
000
Open
230 kV Transmission line is Ready for Energize
7/20/2025
7/20/2025
000
Open
1
000
Open