B. Tasks Table


db_Tasks
Task Name
Duration
Start Date
Due Date
Complete%
Project
Assigned To
Status
Priority
Dependencies
Workload
Route Selection
10
10/15/2024
10/25/2024
000
100
Digital Terain Modeling
24
10/25/2024
11/18/2024
000
100
Plan and Profile Design (PLSCad)
10
11/22/2024
12/2/2024
000
100
Tower Design
45
10/15/2024
11/29/2024
000
99
Soil Investigation
50
11/1/2024
12/21/2024
000
Foundation Design
19
11/1/2024
11/20/2024
000
Procurement Plan
120
12/3/2024
4/2/2025
000
Land Acquisition
58
11/1/2024
12/29/2024
000
UXO
30
12/5/2024
1/4/2025
000
Access Road
90
12/1/2024
3/1/2025
000
Foundation
90
12/1/2024
3/1/2025
000
Tower Erection
90
1/31/2025
5/1/2025
000
Stringing Works
90
4/1/2025
6/30/2025
000
Testing & Commissioning
21
6/30/2025
7/21/2025
000
230 kV Transmission line is Ready for Energize
0
7/20/2025
7/20/2025
000
000