Sprint Report Hungary

Platform Squad Sprint Summary

Completed Sprint: Hungary (04/01/24 -04/12/24)


Estimated Time: 102.5 hrs
Actual Time: 95hrs
Mid Sprint Additions: 9 Tasks. 16.5 hrs
Deloitte Discovery Sessions/Meetings: 27 hours


Key Initiative Focus Items:
Kount
[Kount] Upload Data is currently in Code Review and set to be deployed this Wednesday
Once the above is done, we will be closing out Kount and re-visiting during payment processor initiative
Ketch
Pre-Requisite work has been completed and deployed:
One more pre-req configuration was identified which is currently being worked through:
Overall, we are working at a good pace through Ketch with only the actual data deletion logic needed to be done after this week.

Squad Related Items:
Deloitte user access to our systems
Bug on Order Resumbission
CX Bugs - Order stuck, user unable to update email
Refactor routes for Portal
Clean up work from system actor bug

Upcoming Sprint Plans: Italy (04/15/24-04/26/24)

Estimated Hours: 132hrs
Sprint Focus Items:
Continuation of Ketch implementation and finish up prerequisite work
Close out Kount
CX Portal updates

Site Squad Sprint Summary

Completed Sprint: Hungary (04/01/24 -04/12/24)


Estimated Time: 115 hours
Actual Time: 137 hours
Mid-Sprint Additions: 5 tasks, added 9 hours
Deloitte Discovery Sessions/Meetings: 27 hours

Key Initiative Focus Items:
Release of Site Experience CLP, Navigation and Show All pages
Working on Site Experience Beard Hedger PDP
Meetings and documentation created for Deloitte/Shopify project
[LM 4.0 Pro, LM 3.0 Plus, SS Blade 2.0] [EU, UK, AU, EU, SG, ZA, MENA] complete, ready for 4/16 release

Squad Related Items:
Bug with System Actor created a lot of clean-up work
Addressed issue with Lost Transactions (release 4/16)
Began work with PHP Bundle SKUs
Updated TCS Video

Upcoming Sprint Plans: Italy (04/15/24-04/26/24)

Estimated Hours: 127 hours
Sprint Focus Items:
Beginning Site Experience Beard Hedger PDP Test
LM 5.0 + BH & LM 5.0 + Handyman - US,CA Release
Finish PHP Bundle SKUs work
Prep scripts for Skinsafe Blade Migration
Influencer Contact Page update
Updating checkout cart functionality

OPS Squad Sprint Summary

Completed Sprint: Hungary (04/01/24 -04/12/24)

Estimated Sprint Time: 73 hrs
Actual Sprint Time: 92 hrs
Mid-Sprint Additions: 11 unplanned tasks added 16 hrs
Deloitte Discovery Sessions/Meetings: 19 hrs and 30mins (accounted for separate from sprint time)

Key Initiative Focus Items:
Meetings for Deloitte Discussions Related to Shopify & PPI Project (see hrs below)

Sprint Focus Items:
Added the concept of rejection to our Maersk integration
Developed SEKO integration retry for retrieving orders from Shopify
Updated CS US Shopify tagging flow to include all non-sellable SKUs
Resolved order routing switches not working
Migrated orders from Maersk to FSD
Cleaned up SEKO 430 errors

Upcoming Sprint Plans: Italy (04/15/24-04/26/24)

Estimated Sprint Hours: 80 hrs
Sprint Focus Items:
O2C inventory dashboard bug fixes
Updating our Order Journey to unlock US distribution tool enhancements in the next sprint.
Wrapping up Maersk address correction automation w/ SRE
[Kount] Create 'cancel_shipment' endpoint