Share
Explore

Sprint Report France

Platform Squad Sprint Summary

Completed Sprint: France (3/4/24 - 3/15/24)


Estimated Time: 102hrs
Actual Time: 117hrs
Tasks added mid-sprint: 13 Tasks, 32.5hrs

Key Initiative Focus Items:
Ketch
Continuing on the MongoDB updates, set to deploy on 3/26
spilled over 4 hours into the next sprint. Set to be complete by the end of the month
The next and final step will be setting up the actual data deletion. The current LOE is unknown.
Kount
US Distro Tool
Preview links expected today for QA. Planning to deploy next week
Squad Related Items:
13 unplanned Tasks, totaling 32.5hrs
NX Upgrade is fully deployed and we resolved the post launch bugs
430 Errors in Shopify.

Upcoming Sprint Plans: Greece: (3/18/24 - 3/29/24)

Estimated Hours: 129hrs
Sprint Focus Items:
430 Errors in Shopify (P1)
Continuation on Ketch and Kount implement
Centralize Authentication/Authorization

Site Squad Sprint Summary

Completed Sprint: France (3/4/24 - 3/15/24)


Estimated Time: 108.5hrs
Actual Time: 106hrs
Tasks added mid-sprint: 6 tasks, 12.5 hrs

Key Initiative Focus Items:
Site Experience: PDP Implementation
LM 4.0 Pro, LM 3.0 Plus, SS Blade 2.0 Launch
Squad Related Items:
Add product data to Strapi
ABLR updates
Lost Transactions
PHP Bundle Sku

Upcoming Sprint Plans: Greece: (3/18/24 - 3/29/24

Estimated Hours: 81hrs
Sprint Focus Items:
Site Experience: PDP Implementation
LM 4.0 Pro, LM 3.0 Plus, SS Blade 2.0 - INTL
Strapi Plug-in Exploration

OPS Squad Sprint Summary

Completed Sprint: France: 3/4/24 - 3/15/24

Estimated Time: 90 hrs and 10 mins
Actual Time: 81 hrs and 44 mins
Tasks added mid-sprint: 13 tasks, 21hrs (see below

Key Initiative Focus Items:
US Distribution Tool Development
Squad Related Items:
13 Unplanned Tasks added 20 hrs and 29 mins.
11 CX Bugs, 2 Bulk Order Re-routing Requests, 2 Cleanup Task for Shopify 430/SEKO Errors
We were able to absorb the time added due to unexpected overlap/efficiencies found in the US Distribution Tool development that reduced the # of hours for 1 subtask significantly! However, 1 task is spilling over to the next sprint.

Upcoming Sprint Plans: Greece: 3/18/24 - 3/29/24

Estimated Hours: 62 hrs and 45 mins
Hours have been scaled back to regular capacity (80 hrs) and reduced to account for upcoming PTO...
Riley PTO: 3/19-3/22
Connor PTO: 3/21-3/22
Sprint Focus Items:
Deploying the US Distribution Tool
INTL SEKO Loqate Data Base Scan
Reducing Process Rate for FSD Tracking Info
Automating Maersk Address Corrections