Скрины перевод

icon picker
Стендап с заказчиком перевод

Срок:
January 10-24, 2024
Поручения и ключевые результаты (для ГН) 2
0
Stream
Tasks
Status
Blocked
Plan
Forecast / actual
Responsible
Design session
3
Propose a procedure for communication with BC participants (follow-up)
In work
Jul 5
Jul 1
4
Vasily Skalon
Ensure that stakeholders are informed about the procedure for passing the "Design" stage and the decisions made at it
Acceptance
Jun 24
Jun 24
0
Andrey Malakhov
Think about how to involve the working group in the future
To do
Jun 30
Vasily Skalon
Change management
5
Prepare a list of questions for the Board members
In work
Jul 5
Jul 5
0
Vasily Skalon
Examine the input to the internal kick-off, provide feedback for inconsistencies in the approach
In work
Jun 27
Jun 28
-1
Vasily Skalon
Conduct a "methodological review" of projects that completed the "7 Keys" questionnaire
In work
Jun 28
Jun 28
0
Vasily Skalon
Prepare a slide on active management attention. How will the problem of RP be solved?
Postponed
Jun 24
Vasily Skalon
Correct in the presentation for the Kick-off a slide about the obligations of the participants based on the “SUE” preza
Acceptance
Jun 28
Jun 26
2
Vasily Skalon
Implementation
2
Make a list of additional questions that can be clarified during the review
In work
Jun 24
Jul 4
-10
Vasily Skalon
Calibrate the quick wins plan by the number of events per month
In work
Jun 21
Jun 24
-3
Vasily Skalon
Project management
2
Sign NDA
In work
Jun 28
Jun 28
0
Vasily Skalon
Prepare a list of open questions (hypotheses to be tested) for the 2nd stage of the project
To do
Jun 24
Jun 24
0
Andrey Malakhov
Methodology
4
Refine the visualization of examples of applying the complexity factors model, taking into account the new methodological concept of organizational project management.
In work
Jun 27
Jun 27
0
Supplement the analytical note on the registry of roles with statistical data (how many duplicates, frequency of other problematic points)
In work
Jun 24
Jun 24
0
Anna Bertova
Work on the issue of including in the project management approach a classification of projects that will affect the mandatory elements of project management. Work out the basis for the classification.
Postponed
Jun 24
Andrey Malakhov
Distribute as-is roles according to the target list of project roles approved by AM and BC (grouping in the code)
To do
Jun 24
Jun 27
-3
Anna Bertova