Task Plan
Task Plan
Project
Stage
Major Tasks
Team
Days Estimate
Start Date
Due Date
Status
Assigned Team
Notification Sent
Project
Stage
Major Tasks
Team
Days Estimate
Start Date
Due Date
Status
Assigned Team
Notification Sent
Website Facelift - Phase 2
3
Content
Email Response Template
Digital
00
15
Thu, Sep 14
Fri, Sep 29
Done
DR
Dana Romerosa
Notify user
Website Populating
Update copy for FAQs
Digital
00
5
Thu, Sep 14
Tue, Sep 19
Not Started
Anna Nguyen
Notify user
Website Populating
Update copy for Accessories & Cabin Filters
Digital
00
2
Mon, Oct 2
Wed, Oct 4
Not Started
Anna Nguyen
Notify user
4
Design
UX & Wireframe for Contact Us Page, Manage My Booking, Glazing Chat & FAQs, Become a Member
Digital
00
3
Tue, Aug 22
Fri, Aug 25
Done
Anna Nguyen
Notify user
Website Populating
Action Feedback - Phase 1
Digital
00
7
Fri, Oct 6
Fri, Oct 13
Done
Anna Nguyen
Notify user
Website Populating
Update copy for About Us - Community Page
Digital
00
2
Tue, Oct 10
Thu, Oct 12
Not Started
Anna Nguyen
Notify user
Digital Checklist
Sitemap & SEO check
Digital
00
4
Mon, Oct 2
Fri, Oct 6
Not Started
Notify user