Skip to content
Home Reno 1.0
Share
Explore
Home

To Do Lists

Tasks due in the next two weeks
Show tasks for:
All
Upcoming tasks
5
Search
Home Goal
Who?
Task
Progress
Start Date
End Date
Notes
1
Garden storage
MB
Plan garden shed (sketches)
2021-07-18
2021-07-30
2
Update entryway
MB
Add legs to cabinet
2021-07-22
2021-07-30
3
Building work
MB
Confirm dates with Ian to build
2021-07-24
2021-07-31
4
Declutter
MB
Put excess things on marketplace — take photos, upload
2021-07-25
2021-08-01
5
Front garden upgrade
MB
Add row no. 5
2021-07-25
2021-08-01
6
Remove fireplace
MB
Put fireplace on marketplaces
2021-07-25
2021-08-01
7
A floor that doesn’t squeak
Insulate upstairs floors
2021-07-26
2021-08-02
8
Maintenance
MB
Reinforce bed
2021-07-26
2021-08-02
9
Garden maintenance
MB
Add gravelboard
2021-07-28
2021-08-04
10
Garden storage
MB
Buy/arrange materials for shed
2021-07-30
2021-08-06
11
Building work
MB
Finalise and submit plans
2021-07-31
2021-08-07
12
Front garden upgrade
MB
Add row no. 6
2021-08-01
2021-08-08
13
Garden storage
MB
Remove tree stump
2021-08-02
2021-08-09
14
Brighten landing / stairwell
MB
Measure and plan sun tunnel
2021-08-02
2021-08-09
15
Decorate main bedroom
MB
Prime walls
2021-08-02
2021-08-09
16
Decorate main bedroom
MB
Finalise & buy paint
2021-08-02
2021-08-09
17
Building work
MB
Buy needed materials
2021-08-02
2021-08-09
18
Declutter
MB
Rearrange Ivar shelves
2021-08-02
2021-08-09
19
Pergola
MB
Plan pergola design
2021-07-25
2021-08-09
20
Brighten landing / stairwell
MB
Clear loft space for where tunnel will be
2021-08-02
2021-08-09
21
Decorate Myles’ room
MB
Find, wash and hang curtains
2021-08-02
2021-08-09
22
Garden storage
MB
Level area for shed
2021-07-26
2021-08-10
23
Update entryway
MB
Repaint mirror
2021-08-03
2021-08-10
24
A floor that doesn’t squeak
Lay down underlay
2021-08-04
2021-08-11
25
Redo bathroom
MB
Lift floor
2021-08-02
2021-08-13
26
A floor that doesn’t squeak
Install floor boards
2021-08-07
2021-08-13
27
Garden storage
MB
Build shed
2021-08-07
2021-08-14
28
Decorate main bedroom
MB
Clean muck off walls, remove air bubbles.
2021-07-28
2021-08-15
29
Front garden upgrade
MB
Add row no. 7
2021-08-08
2021-08-15
30
Decorate main bedroom
MB
Add shelves
2021-08-09
2021-08-16
31
Decorate main bedroom
MB
Paint
2021-08-09
2021-08-16
32
Bedroom storage
MB
Receive wardrobes
2021-08-18
2021-08-18
33
Front garden upgrade
MB
Add row no. 8
2021-08-15
2021-08-22
34
A floor that doesn’t squeak
Install skirting
2021-08-16
2021-08-23
35
Upgrade ceilings and walls
MB
Confirm dates with plasterer
2021-08-16
2021-08-23
36
Building work
MB
Clear living area as needed
2021-08-16
2021-08-23
37
Upgrade laundry room
MB
Add table top
2021-08-16
2021-08-23
38
Pergola
MB
Buy materials
2021-08-09
2021-08-23
39
Update entryway
MB
Buy paint
2021-08-18
2021-08-25
40
Refloor downstairs
Finalise (underfloor) heating
2021-08-18
2021-08-25
41
Decorate Myles’ room
MB
Shorten bed
2021-08-19
2021-08-26
42
Bedroom storage
MB
Clear out existing clothes rails
2021-08-23
2021-08-27
43
Decorate Myles’ room
MB
Decide on pattern
2021-08-16
2021-08-27
44
Bedroom storage
MB
Measure, shorten and install wardrobes
2021-08-23
2021-08-27
45
New kitchen
MB
Plan new kitchen
2021-08-16
2021-08-30
46
Update entryway
MB
Remove wallpaper
2021-08-18
2021-08-30
47
Front garden upgrade
MB
Plan stairs and fence
2021-08-24
2021-08-31
48
Front garden upgrade
MB
Sow seeds for grass and wildflowers for next year
2021-09-01
2021-09-01
49
Building work
MB
Building works take place
2021-08-26
2021-09-02
50
Upgrade ceilings and walls
MB
Buy materials
2021-08-26
2021-09-02
51
Bedroom storage
MB
Install insides of wardrobes
2021-08-30
2021-09-03
52
Remove fireplace
MB
Remove fireplace
2021-08-30
2021-09-06
53
Pergola
MB
Build pergola
2021-08-23
2021-09-06
54
Front garden upgrade
MB
Buy materials for stair and fence
2021-08-31
2021-09-07
55
Decorate Myles’ room
MB
Buy paint
2021-08-27
2021-09-07
56
New kitchen
MB
Order kitchen cabinets
2021-08-30
2021-09-13
57
Front garden upgrade
MB
Build stairs and fence
2021-09-07
2021-09-14
58
Upgrade ceilings and walls
MB
Plastering works take place
2021-09-07
2021-09-14
59
Redo bathroom
Redo sink pipes from pex bit to top
2021-09-03
2021-09-17
60
Decorate Myles’ room
MB
Paint
2021-09-07
2021-09-18
61
Decorate Myles’ room
MB
Install ceiling light
2021-09-07
2021-09-18
62
Update entryway
MB
Wallpaper
2021-09-18
2021-09-25
63
Update entryway
MB
Paint
2021-09-18
2021-09-25
64
Refloor downstairs
Lay down underlay
2021-09-16
2021-09-26
65
Refloor downstairs
Lay down floor boards
2021-09-27
2021-10-07
66
New kitchen
MB
Install kitchen
2021-10-08
2021-10-15
67
Brighten landing / stairwell
Execute project brighten landing
2021-09-20
2021-11-01
68
Front garden upgrade
MB
Choose and order apple tree
2021-10-25
2021-11-05
69
Front garden upgrade
MB
Plant apple tree
2021-11-15
2021-11-22
No results from filter
4 week view
5
Search
Plan garden shed (sketches)
Add legs to cabinet
Confirm dates with Ian to build
Put excess things on marketplace — take photos, upload
Add row no. 5
Put fireplace on marketplaces
Insulate upstairs floors
Reinforce bed
Add gravelboard
Buy/arrange materials for shed
Finalise and submit plans
Add row no. 6
Remove tree stump
Measure and plan sun tunnel
Prime walls
Finalise & buy paint
Buy needed materials
Rearrange Ivar shelves
Plan pergola design
Clear loft space for where tunnel will be
Find, wash and hang curtains
Level area for shed
Repaint mirror
Lay down underlay
Lift floor
Install floor boards
Build shed
Clean muck off walls, remove air bubbles.
Add row no. 7
Add shelves
Paint
Receive wardrobes
Add row no. 8
Install skirting
Confirm dates with plasterer
Clear living area as needed
Add table top
Buy materials
Buy paint
Finalise (underfloor) heating
Shorten bed
Clear out existing clothes rails
Decide on pattern
Measure, shorten and install wardrobes
Plan new kitchen
Remove wallpaper
Plan stairs and fence
Sow seeds for grass and wildflowers for next year
Building works take place
Buy materials
Install insides of wardrobes
Remove fireplace
Build pergola
Buy materials for stair and fence
Buy paint
Order kitchen cabinets
Build stairs and fence
Plastering works take place
Redo sink pipes from pex bit to top
Paint
Install ceiling light
Wallpaper
Paint
Lay down underlay
Lay down floor boards
Install kitchen
Execute project brighten landing
Choose and order apple tree
Plant apple tree
Jul 2021
Aug 2021
Sep 2021
Oct 2021
Nov 2021
Dec 2021
Plan garden shed (sketches)
Add legs to cabinet
Confirm dates with Ian to build
Put excess things on marketplace — take photos, upload
Add row no. 5
Put fireplace on marketplaces
Insulate upstairs floors
Reinforce bed
Add gravelboard
Buy/arrange materials for shed
Finalise and submit plans
Add row no. 6
Remove tree stump
Measure and plan sun tunnel
Prime walls
Finalise & buy paint
Buy needed materials
Rearrange Ivar shelves
Plan pergola design
Clear loft space for where tunnel will be
Find, wash and hang curtains
Level area for shed
Repaint mirror
Lay down underlay
Lift floor
Install floor boards
Build shed
Clean muck off walls, remove air bubbles.
Add row no. 7
Add shelves
Paint
Receive wardrobes
Add row no. 8
Install skirting
Confirm dates with plasterer
Clear living area as needed
Add table top
Buy materials
Buy paint
Finalise (underfloor) heating
Shorten bed
Clear out existing clothes rails
Decide on pattern
Measure, shorten and install wardrobes
Plan new kitchen
Remove wallpaper
Plan stairs and fence
Sow seeds for grass and wildflowers for next year
Building works take place
Buy materials
Install insides of wardrobes
Remove fireplace
Build pergola
Buy materials for stair and fence
Buy paint
Order kitchen cabinets
Build stairs and fence
Plastering works take place
Redo sink pipes from pex bit to top
Paint
Install ceiling light
Wallpaper
Paint
Lay down underlay
Lay down floor boards
Install kitchen
Execute project brighten landing
Choose and order apple tree
Plant apple tree

Want to print your doc?