Will Curry - Delivery Dashboard Timeline - SE

Target Delivery Date:
9/3/2024
CFM Start Assembly Date:
8/19/2024

Model:


WC-SE-Delivery-Timeline
Submit PO to CFM
CFM Prep
Verify Stocked Goods Inventory
Order Trailer Parts
Deliver Trailer Parts
Build and Paint Trailer
Order Assembly Parts
Deliver Assembly Parts
Composite Shell (Build, Paint, Prep)
Composite Rear Door
Prep Floors
Prep Walls
Prep Windows
Prep Electrical
Verify Assembly Components
Ready to Build
NS-1 SE Rough Assembly
NS-1 SE Finish Assembly
NS-1 SE QE
NS-1 SE Delivery
2023
2024
2025
March
April
May
June
July
August
September
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
April
May
June
July
August
September
27
3
10
17
24
1
8
15
22
29
5
12
19
26
3
10
17
24
31
7
14
21
28
4
11
18
25
2
9
16
23
30
6
13
20
27
4
11
18
25
1
8
15
22
29
5
12
19
26
4
11
18
25
1
8
15
22
29
6
13
20
27
3
10
17
24
1
8
15
22
29
5
12
19
26
2
9
16
23
30
7
14
21
28
4
11
18
25
2
9
16
23
30
6
13
20
27
3
10
17
24
3
10
17
24
31
7
14
21
28
5
12
19
26
2
9
16
23
30
7
14
21
28
4
11
18
25
1
8
15
22
29
Submit PO to CFM
CFM Prep
Verify Stocked Goods Inventory
Order Trailer Parts
Deliver Trailer Parts
Build and Paint Trailer
Order Assembly Parts
Deliver Assembly Parts
Composite Shell (Build, Paint, Prep)
Composite Rear Door
Prep Floors
Prep Walls
Prep Windows
Prep Electrical
Verify Assembly Components
Ready to Build
NS-1 SE Rough Assembly
NS-1 SE Finish Assembly
NS-1 SE QE
NS-1 SE Delivery
Quarter
TodayFit

WC-Pro-Delivery-Task Tracker
Item
Status
Start
Duration
Owner
Depends on
Submit PO to CFM
7/9/24
-
CFM Prep
7/12/24
9 days
Verify Stocked Goods Inventory
8/6/24
11 days
Order Trailer Parts
7/12/24
8 days
Deliver Trailer Parts
7/21/24
1 day
Build and Paint Trailer
7/22/24
14 days
Order Assembly Parts
7/20/24
17 days
Deliver Assembly Parts
8/6/24
1 day
Composite Shell (Build, Paint, Prep)
7/21/24
21 days
Composite Rear Door
7/21/24
21 days
Prep Floors
8/17/24
7 days
Prep Walls
8/17/24
7 days
Prep Windows
8/8/24
7 days
Prep Electrical
8/8/24
7 days
Verify Assembly Components
8/7/24
12 days
Ready to Build
8/24/24
-
NS-1 SE Rough Assembly
8/25/24
4 days
NS-1 SE Finish Assembly
8/29/24
4 days
NS-1 SE QE
9/2/24
2 days
NS-1 SE Delivery