Sprint Report - February 2nd

Dates: 2/2/2026 - 2/8/2026 ​Goal: Unmet. ​Reason: We have shipped, completed development of many minor enchancements and fixed production bugs. However, a major release item “Proposal v2” was delayed again. Recent reviews from Orvi and Hasan point out that there are a number of things which needs to be done before we release this.

Planned Work

Release (5/6)

AGH-781 - Show client name in task list (inside Order)
Target: Release | Outcome: Done | Hours: — | Links: Planned Owners: Farin | Actual Contributors: Farin, Nafi, Hasan ​Notes: —
AGH-5087 - DataFast Payment Integration (app)
Target: Release | Outcome: Done | Hours: — | Links: Planned Owners: Hasan | Actual Contributors: Hasan ​Notes: —
AGH-4994 - [Enhancment] Improve usability by making “Send Invitation Email” text clickable to check/uncheck the checkbox of client module
Target: Release | Outcome: Done | Hours: — | Links: Planned Owners: Hasan | Actual Contributors: Hasan, Suchi ​Notes: —
AGH-5141 - Allow agency to set a default login route for client
Target: Release | Outcome: Done | Hours: — | Links: Planned Owners: — | Actual Contributors: Hasan ​Notes: This was a sudden enchancement we introduced for a client Hasan, an optional + backward compatible feature.
AGH-5167 - Add terms & condition acknowledgement on Agency subscription purchase
Target: Release | Outcome: Done | Hours: — | Links: Planned Owners: Hasan | Actual Contributors: Hasan ​Notes: Hasan updated Business details in Stripe, make ToS aggrement required and updated management in details on the situation.
AGH-4813 - Proposal V₂
Target: Release | Outcome: Incomplete | Hours: — | Links: Planned Owners: Atik, Shakib | Actual Contributors: Atik, Shakib, Farin, Nafi, Suchi, Hasan, Orvi ​Notes: Despite being main focus of the team, it has been incomplete. Recent reviews from Orvi and Hasan point out that there are a number of things which needs to be done before we release this.
And on the last day of the Sprint Hasan pushed team again for the overall timeline of the AppSumo launch plan. It slightly hampered the proposal feature work.
It is to be released in next sprint (Remote 1).

Development (3/6)

AGH-5140 - Lead followup automation POC
Target: Development | Outcome: Done | Hours: — | Links: Planned Owners: Hasan | Actual Contributors: Hasan ​Notes: —
AGH-5251 - Stripe 3DS
Target: Development | Outcome: Done | Hours: — | Links: Planned Owners: Hasan | Actual Contributors: Hasan ​Notes: 3DS was bundled with ACH, SEPA, iDEAL. As per the sprint goal, Hasn has separated the files and changes from the bundle to 3DS only and sent to Test.
AGH-5035 - Real-time Update issue for task requests in order details feature under order module
Target: Development | Outcome: Not Started | Hours: — | Links: Planned Owners: Shakib | Actual Contributors: — ​Notes: Hasan reached out to Shakib (late) to understand why this has been circulating for some time now and asked if they need Hasan’s help on this.
AGH-5164 - Disallow agency workspaces in discovery via robots.txt
Target: Development | Outcome: Incomplete | Hours: — | Links: Planned Owners: Hasan | Actual Contributors: Hasan ​Notes: Hasan started this but later deprioritized over production bugs and other works.
AGH-5243 - Add Package information in Invoice event
Target: Development | Outcome: Done | Hours: — | Links: Planned Owners: Hasan | Actual Contributors: Hasan ​Notes: It was introduced in Manual order flow so that Manual Order Invoices can be corrected created with Tax in Xero.
AGH-4903 - Public Form Automation
Target: Development | Outcome: In Progress | Hours: — | Links: Planned Owners: Atik | Actual Contributors: Atik, Farin ​Notes: Team’s major focus has been Proposal v2

UX (0/2)

AGH-5040 - Need to Display Total Count as module wise /depends on module(UI imrovement)
Target: UX | Outcome: In Progress | Hours: — | Links: Planned Owners: Sharif | Actual Contributors: Sharif ​Notes: Sharif Changed status to Dev, Hasan requested Figma file.
AGH-742 - Allow negative filter
Target: UX | Outcome: In Progress | Hours: — | Links: Planned Owners: Sharif | Actual Contributors: Sharif ​Notes: Sharif Changed status to Dev, Hasan requested Figma file.

Unplanned Work

Production Bug Fix (8/12)

AGH-5153 - Deleted members show as “Undefined Undefined” in Ticket/Task comments and Activity Log
Target: Production Bug Fix | Outcome: Incomplete | Hours: — | Links: Planned Owners: — | Actual Contributors: Farin, Nafi ​Notes: Bug fix was applied but QA found case and sent to Revist
AGH-5191 - Changing Package Icon Color Updates Background Instead of Icon
Target: Production Bug Fix | Outcome: Done | Hours: — | Links: Planned Owners: — | Actual Contributors: Hasan, Nafi ​Notes: —
AGH-5209 - Intake/Order Form Issues
Target: Production Bug Fix | Outcome: Done | Hours: — | Links: Planned Owners: — | Actual Contributors: Hasan, Nafi ​Notes: —
AGH-5043 - Failed to submit time entry for Task without Order ID
Target: Production Bug Fix | Outcome: Done | Hours: — | Links: Planned Owners: — | Actual Contributors: Farin, Nafi, Suchi ​Notes: —
AGH-5016 - Workspace default currency is not auto-selected during service creation
Target: Production Bug Fix | Outcome: Incomplete | Hours: — | Links: Planned Owners: — | Actual Contributors: Farin, Nafi ​Notes: Bug fix was applied but QA found case and sent to Revist
AGH-5212 - Task component issue
Target: Production Bug Fix | Outcome: Done | Hours: — | Links: Planned Owners: — | Actual Contributors: Hasan ​Notes: —
AGH-5239 - Wilfried Streiner: Onelabs
Target: Production Bug Fix | Outcome: Done | Hours: — | Links: Planned Owners: — | Actual Contributors: Hasan ​Notes: Hasan migrated files back caused by recently fixed File missing bug in Task and Portfolio.
AGH-5169 - Client does not receive in-app notification after task status is set to review, despite notification being enabled
Target: Production Bug Fix | Outcome: Incomplete | Hours: — | Links: Planned Owners: — | Actual Contributors: Hasan ​Notes: Hasan checked and found the scope is more than what is visible on issue. Along with the reported bug fix, FE changes were made as well to handle Task notifications which has no Order. Team was informed in Huly in details about the situation.
This was sent to Test on the last day.
AGH-5152 - Manual Time Entry: End Time Is Disabled When Start Time Is Set to Today at 12:00 PM
Target: Production Bug Fix | Outcome: Done | Hours: — | Links: Planned Owners: — | Actual Contributors: Shakib, Suchi, Hasan ​Notes: —
AGH-5193 - Default Package Icon Is Replaced by an Another Icon on Package Creation
Target: Production Bug Fix | Outcome: Done | Hours: — | Links: Planned Owners: — | Actual Contributors: Hasan, Nafi ​Notes: —
AGH-5132 - Showing Upsell instead of Add On in the heading of Add On in Manual Order
Target: Production Bug Fix | Outcome: Done | Hours: — | Links: Planned Owners: — | Actual Contributors: Farin, Nafi ​Notes: —
AGH-5161 - Client won’t be able to edit tickets that are created by Agency
Target: Production Bug Fix | Outcome: Incomplete | Hours: — | Links: Planned Owners: — | Actual Contributors: Farin, Nafi ​Notes: Bug fix was applied but QA found case and sent to Revist