BD_CRONOGRAMA_SEBRAE_FACHADA



BD_CRONOGRAMA_SEBRAE
ID_ETAPA
ETAPA DO CRONOGRAMA
STATUS
INÍCIO
DATA FIM
DURAÇÃO
RESPONSÁVEL
TAG_PROJETO
DEPENDÊNCIA
ETP-#1
PROJ. ARQUITETURA
09/10/2025
08/11/2025
30 days
ETP-#2
PROJ. COMUNICAÇÃO VISUAL
08/11/2025
28/11/2025
20 days
ETP-#3
PROJ. LUMINOTÉCNICA
08/11/2025
28/11/2025
20 days
ETP-#4
PROJ. PAISAGISMO
08/11/2025
28/11/2025
20 days
ETP-#5
RENDER
08/11/2025
28/11/2025
20 days
ETP-#6
ENTREGA 1 (Milestone)
28/11/2025
28/11/2025
-
ETP-#7
PROJ. METÁLICA
29/11/2025
21/12/2025
22 days
ETP-#8
PROJ. NSTALAÇÕES ELÉTRICAS
29/11/2025
21/12/2025
22 days
ETP-#9
PROJ. IMPERMEABILIZAÇÃO
29/11/2025
21/12/2025
22 days
ETP-#10
CADERNO DE ENCARGOS
21/12/2025
05/01/2026
15 days
ETP-#11
ENTREGA 2 (Milestone)
05/01/2026
05/01/2026
-
ETP-#12
PLANILHA ORÇAMENTÁRIA
05/01/2026
29/01/2026
24 days
ETP-#13
ENTREGA 3 (Milestone)
30/01/2026
30/01/2026
-