🎯 Key objectives
1
2
3
4
Objectives
Achieve industry leading standards for health, safety and wellbeing
Complete the Project on Time
Develop exceptional interfaces and collaborative relationships
Implement Jira System inside Link Alliance
There are no rows in this table


Milestones by objective
1

Filter by quarter :
All

Success plan
1
Achieve industry leading standards for health, safety and wellbeing
Complete the Project on Time
Develop exceptional interfaces and collaborative relationships
Implement Jira System inside Link Alliance
Ensure the Alliance’s health & safety expectations are reiterated in engagements for System works (Project wide)
ALL
Martin Kauffmann
000
51
HSE focus during each site visit
ALL
Martin Kauffmann
000
51
Provide a site safety report monthly
ALL
Martin Kauffmann
000
Milestone N/A
Review of project specifications, project drawings as necessary.
ALL
Martin Kauffmann
000
75
Support Verification Lead to ensure quality control is progressing
ALL
Martin Kauffmann
000
50
Support Verification Lead on focusing in OC3.2 works for MC40 & Porters Footbridge Handover
Q2
Martin Kauffmann
000
100
Done
Support Verification Lead on focusing in OC4.1 works for Tunnels E&B and SIG Installation works
Q4
Martin Kauffmann
000
25
Main ongoing activity
Support Verification Lead to ensure completion and closure of the quality pack before T&C for E&B and SIG activities
ALL
Martin Kauffmann
000
80
OC 3.2 Done OC 4.1 day to day updates for QRP completion next Feb.
Support delivery team to complete Go/NoGo and Takeover process in due time. Streamline theses process for Delivery team to complete process faster.
ALL
Martin Kauffmann
000
50
Support Verification Lead as per Delivery work priorities, attend weekly follow-up meetings
ALL
Martin Kauffmann
000
100
not concerned by Weekly follow up
Develop workflow/relationship with DLV team (E&B and SIG ) for any technical issues
ALL
Martin Kauffmann
000
100
Build core of Jira System to streamline snagging process
Q1
Martin Kauffmann
000
100
Done
Develop export features for users to share information/KPI data to external users
Q1
Martin Kauffmann
000
100
Done
Schedule and perform company-wide Jira training.
Q2
Martin Kauffmann
000
90
All training for LKA done, External training in going
Administration and technical advisor for Jira application
ALL
Martin Kauffmann
000
100
Expand Jira system to company-wide needs
Q3
Martin Kauffmann
000
0
Milestone in discussion