Pass = Works as expected and per the Sprint work item
Fail = Has to be fixed and does not work as expected based on the agreed work item. If too big to fix push to next sprint and change status to "aborted"
Partial = Some of the functionality works, and it passes but need to improve in future releases
Skip = Not relevant for this sprint of previous sprints
Aborted = Can't test due to other fails, or fix is too big and needs to be aborted and not released
SF Staging Testing
2B staging 02/12/21 - 17:54
151 tests
10 Fails
131 passed
Use version history to track back
3A staging 21 / 12 / 21
157 tests
7 fails
140 pasts
3A Testing 22/12/21
157 Tests
0 Fails
151 Passed
3B Testing 15:48 09/02/22
178 Tests
14 Fails
155 Passed
4A Testing 18:00 31/03/22
201 Tests
13 Failed
179 Passed
Pass rate 89%
4A Testing 16:00 31/03/22
201 Tests
0 Failed
195 Passed
Pass rate 97%
4B Testing 12:26 07/06/22
222 Tests
15 Failed
202 Passed
Pass rate 91%
SPW Staging Testing
3B Testing 16:11 09/02/22
19 Tests
1 Fails
18 Passed
PROD Testing
3A & 2B Testing 22/12/12 (1st test)
157 tests
4 fails
152 passed
3A & 2B Testing 22/12/12 (1st test)
157 tests
0 fails
156 passed