173 E 90 (AIV)
165 E 90: 1B, 2A, 2B, 3A, 3B, 4A, 4B
Vendor: Paramount
4/25/2021
GC hire plumber to supersede
As of 4/7 GC is hiring Maxwell Plumbing to take over job
173 E 90 (AIV)
165 E 90: 1B, 2A, 2B, 3A, 3B, 4A, 4B
Vendor: Paramount
5/25/2021
Plumber to perform site inspection
Maxwell Plumbing will perform site inspection
173 E 90 (AIV)
165 E 90: 1B, 2A, 2B, 3A, 3B, 4A, 4B
Vendor: Paramount
6/24/2021
Schedule plumbing inspection
Plumber to schedule inspection
173 E 90 (AIV)
165 E 90: 1B, 2A, 2B, 3A, 3B, 4A, 4B
Vendor: Paramount
7/24/2021
Complete Plumbing Signoff
Plumber to request plumbing sign off
173 E 90 (AIV)
165 E 90: 1B, 2A, 2B, 3A, 3B, 4A, 4B
Vendor: Kohn
8/23/2021
Architect to request LOC
Architect to request LOC
173 E 90 (AIV)
167 E 90: 1C
Vendor: ART+1
5/3/2021
Install new gas valve on stove
GC to install new gas valve